=145. Taking Off Hardware.=—The compilation of the estimate schedule
of finishing hardware for a building must be made from the architect’s
plans and specifications. Therefore, where possible, this work should
be done by a hardware expert or salesman, or by some person who has
the ability to read drawings easily and accurately and who is capable
of exercising thoroughness in every detail of the work. The first step
should be to study the specifications relating to the general work,
and especially that portion relating to hardware and carpenter work,
to see whether the latter embodies facts that affect the hardware. If
such is the case, notes should be made of the fact, and in many cases,
by following this rule, miscellaneous information can be gathered that
will be invaluable to the contractor and will prevent much doubt as to
requirements. The drawings should then be examined, to gain familiarity
with the building, the arrangement of the interior, and other details.
Having thus acquired a general understanding of the whole subject, the
compilation of the quantities may begin.
=146.= The list of hardware should be compiled in a systematic manner,
beginning at a definite point in the building and progressing through
the several rooms and floors in a definite order. This will insure the
inclusion of every part of the building and the careful consideration
of every opening or other place where hardware is required. For
example, in the case of a residence, it is customary to commence at
the front entrance, including the front and vestibule doors, passing
thence to the hall, taking each room on the first floor in due order,
passing to the second floor and taking each room on it in like order,
and so on until each floor is covered. The attic and basement are
usually left until last, because they require a simpler class of goods.
The same general system can be followed in the case of hotels, office
buildings, apartment houses, etc., the essential point being that an
orderly method be followed. The rooms should always be taken in natural
sequence, and all openings of similar character totaled and again
counted on the drawing, so that the chances of omission are minimized.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account