Water Supply: the Present Practice of Sinking and Boring Wells: With Geological Considerations and Examples of Wells ExecutedSpon, Ernest
Science
Water Supply: the Present Practice of Sinking and Boring Wells: With Geological Considerations and Examples of Wells Executed
Spon, Ernest
Boring; Water-supply; Wells
With the sheer-frame the boring tools are worked in the same manner as
in the preceding arrangements, Figs. 83, 84; but its portability,
compactness, and adaptation of means to the required end, render its use
desirable wherever it is possible to obtain it.
[Illustration: Driving Ring for wrought-iron Tubes.
Fig. 86.]
When in the progress of the work it is found that the auger does not go
down to the depth from which it was withdrawn, after trial, tubing will
generally be necessary. The hole should be enlarged from the surface,
or, if not very deep, commenced afresh from the surface with a larger
auger, and run down to nearly the same depth; the first length of tube
is then driven into the hole, and when this is effected another tube,
having similar dimensions to the first, is screwed into its upper end,
and the driving repeated, and so on until a sufficient number of pipes
have been used to reach to the bottom of the hole. If the ordinary auger
is now introduced through these tubes it will have free access to the
clay or sand, and after a few feet deeper have been bored another pipe
may be screwed on, and the whole driven farther down. In this way from
10 to 20 feet of soft stratum may be bored through. If the thickness of
the surface clay or sand is considerable the method here mentioned will
not be effective, as the friction of the pipes caused by the pressure
of the strata will be so great that perhaps not more than 80 or 100 feet
can be driven without the pipes being injured. It will then be necessary
to put down the first part of the bore-hole with a large auger, and
drive in pipes of larger diameter; the hole is continued of smaller
diameter, and lined with smaller tubes projecting beyond the large
tubes, as in Fig. 85, until the necessity for their use ceases. It will
be evident that to ensure success the tubing, whatever it is made of,
should be as truly cylindrical as possible, straight, and flush surface,
both outside and in. It will also be evident that in thus joining pieces
of tubing together, the thickness ought to have a due proportion to the
work required, and the force likely to be used in screwing or driving
them down. Wrought-iron tubes, when driven, must be worked carefully, by
means of a ring made of wrought-iron, from 1-1/2 to 2 inches in height
and 3/4 inch thick, and of the form shown in Fig. 86; or driven with a
pipe-dolly such as that in Fig. 80. The ring, or the dolly, is screwed
into the lowermost boring rod and worked at the same rate and in a
similar manner to the chisel, due regard being had to the depth at which
the driving is being done, as the weight of the boring rods will
materially affect the strength of the blow delivered. Cast-iron tubing
may be driven hard with a monkey. To withdraw broken or defective
tubing quickly, two hooks attached to ropes are lowered down from
opposite sides of the bore-hole, caught on the rim of the lowermost
tube, and power applied to haul the tubing up bodily.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account