The Offense Section and the Midland Section were concerned with the
manufacture of mustard gas. This work was greatly delayed because
of the unsatisfactory nature of the so-called chlorohydrin process.
Another difficulty was the development of a satisfactory ethylene
furnace. Finally in February, 1918, Pope in England discovered the
sulfur chloride method of making mustard gas. At once all the energies
of the Research Division were concentrated on this process, and
in March steps were taken to put this process into production. An
experimental plant was established at Cleveland; no attempt was made
to manufacture mustard gas on a large scale, but the results obtained
in the experimental studies were immediately transmitted to the
manufacturing plants at Edgewood Arsenal, the Hastings-on-Hudson plant,
the National Aniline & Chemical Company (Buffalo) plant, and the Dow
Chemical Company (Midland) plant. The details of the work on mustard
gas will be given in a later chapter.
Special investigations were undertaken to develop a booster casing and
adapter for 75 mm. gas shell, and to duplicate the French process of
lining gas shell with glass.
The organization of the Development Division at the signing of the
Armistice was as follows:
Colonel F. M. Dorsey Chief of the Division
Major L. J. Willien Supt., Offense Section
Capt. O. L. Barnebey Supt., Defense Section
Lt. Col. W. G. Wilcox Supt., Experimental Station
Capt. Duncan MacRae Special Investigation Section
Dr. A. W. Smith Midland Section
Capt. J. R. Duff Administrative Section
PROVING DIVISION
The Proving Division had its origin in the decision to build an
Experimental Ground for gas warfare under the direction of the Trench
Warfare Section of the Ordnance Department. While this decision was
reached about September, 1917, actual work on the final location
(Lakehurst, N. J.) was not started until March 26, 1918, and the
construction work was not completed until August 1, 1918. However,
firing trials were started on April 25, 1918, and in all 82 were
carried out.
The Proving Division was created to do two things: To experiment
with gas shell before they reached the point where they could be
manufactured safely in large numbers for shipment overseas; and to
prove gas shell, presumably perfect and ready for shipment, to guard
against any mechanical inaccuracies in manufacture or filling. It
is evident that the second proposition is dependent upon the first.
Shell can not be proved to ascertain the effect of gases under various
conditions and concentrations until the mechanical details of the
shell itself, purely an Ordnance matter, have been standardized.
Unfortunately many of the tests carried out had to do with this very
question of testing Ordnance.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account