Centuries ago it was realized that it would be possible for men to
descend into the open sea if they were protected by a bell-shaped
chamber, for the air trapped in the chamber would furnish them with
oxygen requisite for breathing purposes, and would prevent the water
from drowning them out. This same idea of a diving bell is used on
land when sinking a shaft through quicksand or water-bearing strata. A
large box or caisson is used. (See Figure 43.) This box may be either
cylindrical or rectangular, and it is open at the top and bottom. The
lower edges of the box are shod with steel and form cutting edges that
will sink into the soil that is being excavated. At a height of about
seven feet above the bottom of the box there is a transverse diaphragm
known as the deck, and the space below is known as the working
chamber. This deck is very strongly constructed, as it has to support
the weight of the concrete shaft that is built above it. Laborers,
commonly known as “sand hogs,” enter the working chamber and dig out a
shallow pit in the floor of clay or sand. This pit is then extended to
the cutting edges of the caisson. The caisson thus undermined settles
down into the excavation and another pit is started. In this way, step
by step, the caisson is sunk into the ground. In order to overcome the
friction of the caisson against the sides of the excavation and to
insure its sinking, it is heavily weighted. When water-bearing sand is
reached, compressed air is admitted into the working chamber to force
the water out. When the air pressure is greater than the water pressure
it drives the water out of the sand in the working chamber, so that the
men can work in perfectly dry ground, even though the surrounding sand
may be so saturated with water as to form a quicksand.
Of course the farther the excavation proceeds below the water level the
greater the air pressure required, and the caisson would be blown up
out of the ground by this air pressure or would float on the water were
it not for the weights with which it is loaded. When an open shaft is
to be dug, pig iron is loaded on the caisson to force it down, but in
most work the object is merely to sink a concrete column down to rock
and so the caisson is filled with concrete above the deck. Sections
are added to the caisson as it sinks into the ground, and these
sections are filled with concrete. This method of building the column
facilitates the work of laying the concrete, and at the same time
provides the weight necessary to overcome the buoyancy of the caisson
and the skin friction on the side walls of the excavation.
After the caisson has been carried down to rock and a good seat has
been blasted out of solid rock, the working chamber is completely
filled with concrete and the concrete shaft is thus anchored to the
rock.
THE AIR LOCK
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account