Fig. 26 shows in plan and section a sub-surface irrigation system. The
section, which is drawn to a larger scale than the plan, shows the
settling tank and the adjoining siphon chamber. From this siphon chamber
the effluent sewer carries the discharge from the siphon to the
diverting manhole, at which point the effluent is diverted to the
different portions of the sub-surface tiling.
In Fig. 27 is shown in plan the diverting manhole and a small portion of
the sub-surface tiling system together with a section through the
diverting manhole and one of the lines of distributing tiling.
The main carrier should be of vitrified tile sewer pipe with cemented
joints, and should always have two or more branches at the irrigation
field in order to allow the use of different portions of the field in
turn for three days or a week at a time, thus allowing one of the
portions of the field to be resting for corresponding periods. The
branch carriers should be of vitrified tile also, and should have
cemented joints. If the diameter of the siphon is 5 inches, the main
carrier should be of 8–inch vitrified tile with a fall of at least 6
inches per 100 feet in order to quickly carry the dose from the siphon
chamber to the several lines of sub-surface tiling forming the
distributing system. With 3–inch siphons, a 6–inch main carrier may be
used, but the gradient or fall of the main carrier should then be at
least 12 inches per 100 feet, owing to the smaller capacity of the
6–inch pipe. In placing the siphon in position, when the siphon chamber
is being built, care should be taken to see that the trap or U-shaped
pipe is set plumb or in a vertical position. Concrete should then be
placed around the siphon to hold it in proper position and at the proper
height, and the trap should be filled with water before the bell is
placed in position. The bell should then be placed in position over the
long leg of the trap to prevent the materials used in construction from
being dropped into the siphon. The siphon should be set so that the
lower edge of the bell, or of that portion of the bell under which the
effluent is to flow, is three inches above the floor of the siphon
chamber.
[Illustration: FIG. 28.—Y-Branch of Vitrified Tile Pipe.]
In laying the distributing system, every second or third length of the
branch carriers, according to the porosity of the soil and the spacing
of the lines of distributing tiling, should consist of a Y-branch (see
Fig. 28), to which a one-eighth bend (see Fig. 29) should be fitted if
the lines of lateral tiling are to be laid at right angles to the main
carriers, as shown in Fig. 27; or the lateral tiling may be fitted
directly to the Y-branch if the lateral lines are to be led away from
the carrier at an angle of 45°, as shown in Fig. 30. The Y should branch
from the lower portion of the pipe, as shown in Fig. 28.
[Illustration: FIG. 29—Eighth Bend of Vitrified Tile Pipe.]
[Illustration: FIG. 30.—Sub-surface Tiling.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account