During the first season of work fifty-eight miles on the summit level
were placed under contract, but most of the contractors were compelled
to cease work when the frosts came. In December, 1817, from $200 to
$1,000 each was advanced to contractors with which to buy provisions for
their men; beef, pork, and flour were cheaper at this season than in the
spring, and the roads over which they were to be transported were
likewise better in the winter season than at any other. This first year
of work had brought its lessons; first and foremost it proved what a
tremendous burden lay on the shoulders of the commissioners and
engineers. Contracts innumerable were to be made and signed, calling for
the provision of a hundred necessities: principally for stone, lumber,
and lime; the proper quantities were to be deposited at the proper
places--here in a heavy forest, there beside a swamp, and yonder at the
foot of a hill. The country was quite innocent of anything that
approached such a road as was needed everywhere along the line of work.
It is difficult even to hint at the multitude of perplexing questions
that the builders of the Erie Canal faced and somehow solved. The year
had proved the advisability of discarding the spade and wheelbarrow--the
European implements for canal building--for the plough and scraper. With
the latter tools the work was more quickly done and better; the feet of
the horses drawing them tended to solidify the earth along the
embankments. Three Irishmen finished three rods of the canal, four feet
deep in five and one-half days. Sixteen and one-half days work
accomplished 249-1/2 cubic yards of canal, which at twelve and one-half
cents per yard made $1.80 for each man per day. As the year progressed
it was found that the contracts were inside of the figures of the
estimates originally made.
When the season of 1818 was on, between two and three thousand men and
half that number of horses and cattle were at work. Indeed some of the
contractors had worked all winter, and many had transported the
necessary provisions and tools for the summer's campaign to the points
of work on sleds during the winter. The Genesee Road between Utica and
Syracuse, the most important of all, was useless for heavy loads in the
summer season. During this season the entire Middle Section was put
under contract; the only important change of route was at the Marl
Meadows near Camillus; this swamp without an outlet was avoided by
running a new route through the Salina plains, at an estimated saving of
some $17,000.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account