The few first days after getting fairly established in our habitation
for the season, were occupied in extending the railway to a point on
the northern part of the Rock, somewhat sheltered during certain seas
(see Plate III.), where a crane for stowing the materials previously
to building them had been erected; and thus it was not till the 25th of
May that the first cargo of stones was landed. Next day a crane (then
thirty-four years old), which had been used in the building of the Bell
Rock Lighthouse, was placed on the top of the masonry, and the more
cheering operations of mixing the mortar and of _setting_ stones were
begun.
In spite of the unfavourable state of the weather and the continual
distraction of our exertions, occasioned by storms and the landing of
materials, we continued our operations with such vigour as to complete
the solid part of the masonry of the Tower on the 8th July. Until the
building had reached to the level of 15 feet, the work was carried on
by the use of two jib-cranes, one on the Rock and the other on the
Tower, by means of which latter the stones were _set_, after being
_brought to hand_ by the first. But above that level, _shear-legs_
similar to those used at the Eddystone, were employed. Those shear-legs
were about 50 feet high, and were erected in the situation, at the side
of the Tower, shewn in Plate III. They consisted of two spars attached
at the base to _jointed_ sockets _batted_ into the Rock, and connected
at the top by means of a crosshead of timber. The jointed sockets
permitted the shears to hang forward at any angle suited to the level
and distance of the part of the Tower to be reached; and chain guys
both in front and behind, secured them from falling either backwards or
forwards. At the crosshead hung an iron sheave with a chain, one end
of which was provided with a hook for raising stones, while the other
was wound around the barrel of a _crab machine_ well batted down to the
rock, by working which the blocks were raised to such a level as to
be within reach of the building crane on the top of the masonry. The
_shear-poles_ were used, until the building of the Tower was completed,
to raise the stones the first lift of forty feet above the Rock. In
the later stages of the work, the stones, instead of being taken by
the building cranes directly from the _shear-poles_, were raised from
storey to storey by means of crabs placed inside the Tower, which
worked chains, _reeved_ through sheaves hanging from the end of beams
projecting from the windows. Such beams are called _needles_, and are
described at page 504, and shewn in Plate IX., fig. 3, of my Father’s
Account of the Bell Rock Lighthouse, where they were used for the same
purpose.
~The Waves.~
~Colours of breaking Waves.~
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account