The quarry itself, as already stated, was opened in the face of the
cliff, at a point where the successive beds of solid rock seemed to
promise the fairest prospect of success. The preliminary operation was
to remove a very thin alluvial cover which scarcely concealed from
view a large mass of most beautiful granite, whose reddish colour
is said to have given the name of _Ross_[19] to that part of Mull,
the shores of which everywhere exhibit massive slopes of that fine
rock. The granite is separated very abruptly from the basalts of the
surrounding district, so as to leave the Ross purely granitic; but in
no part of the whole coast, which abounds with creeks and bays, does
the rock appear to be of equal quality, or so conveniently situated
for shipping, and so easily accessible to quarriers, as at the spot
we had chosen. I know of no instance of a quarry so fully answering
the most sanguine expectations as that of the Ross of Mull; and I
have never seen a granite quarry of equally great resources, as
regards both the quantity and the quality of the material produced.
The rock in general yielded easily before well-directed shots, and
was separated into large masses, capable of being advantageously
cut, with little loss of material, into shapely blocks, by means of
wedges, which work remarkably well in that rock. A few weeks after the
quarrying operations had been commenced, a single shot detached 150
tons of excellent stone, in the cutting of which into blocks for the
Lighthouse Tower little loss of material occurred; and in the course
of the season of 1839, although the summer was chiefly spent in the
preliminary works above noticed, the Mull quarries produced nearly as
much workable material for the Lighthouse Tower as the Hynish quarries
had done in three years. In the course of the future working of the
quarry, when it came to be more fully opened, its resources were so
great, that on one occasion a single shot shook about 570 tons, while
another shot detached a mass of 460 tons. In that way, between April
1839 and June 1840, material had been quarried in that single spot,
sufficient to supply 4300 selected blocks, varying in weight from ³⁄₄
ton to 2¹⁄₂ tons each. The average monthly produce of the quarries was
about 400 tons, and there were generally employed in them 26 quarriers,
3 labourers, and 2 smiths. The quantity of gunpowder consumed in the
quarry was small, as it was almost exclusively employed in great bores
about 11 feet deep, for the purpose of detaching large masses which
had no _open side_ and could not be removed by means of the _pinch_ or
_crow-bar_. When a mass of rock had been thus removed, it was cut up
into various portions by means of wedges, and finally subdivided into
blocks, _hammer_ (or as it is called _quarry_) _dressed_, according
to rough moulds, whose dimensions exceeded those of the stones of the
various courses of the building by a quantity which was considered
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account