Stevenson, Robert
Bell Rock Lighthouse (Scotland); Lighthouses -- Scotland
Landed on the Rock, with the three boats belonging to the Tender,
at 5 P. M., and began immediately to bale the water out of the
foundation-pit, with a number of buckets, while the pumps were also
kept in action with relays of artificers and seamen. The work commenced
upon the higher parts of the foundation, as the water left them, but it
was now pretty generally reduced to a level. The pumps were laid in a
diagonal position as represented in Plate XI.; four men wrought at the
cross handle and guided the pump-spear, to which a rope was attached,
and in this manner, about 20 men could be conveniently employed at
each pump, and it is quite astonishing in how short a time so great a
body of water could be drawn off. The water in the foundation-pit at
this time, measured about two feet in depth, on an area of 42 feet in
diameter; and yet it was drawn off in the course of about half an hour.
After this, the artificers commenced with their picks, and continued
at work for two hours and a half, some of the sailors being at the
same time busily employed in clearing the foundation of chips, and in
conveying the irons to and from the smiths on the beacon where they
were sharped. At 8 o’clock, the sea broke in upon us, and overflowed
the foundation pit, when the boats returned to the Tender.
[Sidenote: Thursday, 7th.]
[Sidenote: How employed.]
The landing-master’s bell rung this morning about 4 o’clock, and at 5
the boats landed the artificers, when the pumps and buckets were set
to work to clear the foundation-pit of water. The pumps, as formerly
noticed, were left upon the Rock, being fixed between four bars of
iron, batted or wedged into it, upon which plates were fitted with
forelocks, which kept them from shifting. It was common also to drive
a few wedges of iron between the pumps and these fixtures, for greater
security against their being lifted by the pressure of the water,
which, in spring tides, was from 12 to 14 feet in depth. At half-past
5, the foundation being cleared, the work commenced on the site of the
building. But from the moment of landing, the squad of joiners and
mill-wrights was at work upon the higher parts of the Rock, in laying
the railways, while the anvils of the smiths resounded on the Beacon,
and such columns of smoke ascended from the forges, that they were
often mistaken by strangers at a distance, for a ship on fire. After
continuing three hours at work, the foundation of the building was
again overflowed, and the boats returned to the ship at half-past 8
o’clock. The masons and pickmen had, at this period, a pretty long day
on board of the Tender, but the smiths and joiners were kept constantly
at work upon the Beacon; the stability and great conveniency of which
had now been so fully shewn, that no doubt remained as to the propriety
of fitting it up as a barrack. The workmen were accordingly employed,
during the period of high-water, in making preparations for this
purpose.
[Sidenote: Foundation stone prepared.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account