A 4-foot ditch, in most soils, need be only 20 inches wide at the surface,
and 4 inches at the bottom. This gives a mean width of 12 inches, and
requires the removal of nearly 2-1/2 cubic yards of earth for each rod of
ditch; but an increase to a mean width of 16 inches, (which day workmen
will usually reach, while piece workmen almost never will,) requires the
removal of 3-1/4 cubic yards to the rod. As the increased width is usually
below the middle of the drain, the extra earth will all have to be raised
from 2 to 4 feet, and the extra 3/4 yards will cost as much as a full yard
taken evenly from the whole side, from top to bottom.
In clay soils, free from stones or "hard pan," but so stiff as to require
considerable picking, ordinary workmen, after a little practice, will be
able to dig 3-1/2 rods of ditch per day, to an average depth of
3.80,—leaving from 2 to 3 inches of the bottom of 4-foot ditches to be
finished by the graders. This makes the cost of digging about 43 cents per
rod. In loamy soil the cost will be a little less than this, and in very
hard ground, a little more. In sandy and peaty soils, the cost will not be
more than 30 cents. Probably 43 cents would be a fair average for soils
requiring drainage, throughout the country.
This is about 17 cents for each yard of earth removed.
In soft ground, the caving in of the banks will require a much greater
mean width than 12 inches to be thrown out, and, if the accident could not
have been prevented by ordinary care on the part of the workman, (using
the bracing boards shown in Fig. 28,) he should receive extra pay for the
extra work. In passing around large stones it may also be necessary to
increase the width.
The following table will facilitate the calculations for such extra work:
CUBIC YARDS OF EXCAVATION IN DITCHES OF VARIOUS WIDTH.
_Length of 12 _Inches 18 _Inches 24 _Inches 30 _Inches 36 _Inches
Ditch._ Wide._ Wide._ Wide._ Wide._ Wide._
Yds. Feet. Yds. Feet. Yds. Feet. Yds. Feet. Yds. Feet.
1 Yard. 0 12 0 18 0 24 1 3 1 9
1 Rod. 2 12 3 18 4 24 6 3 7 9
Men will, in most soils, work best in couples,—one shovelling out the
earth, and working forward, and the other, (moving backward,) loosening
the earth with a spade or foot-pick, (Fig. 41.) In stony land, the men
should be required to keep their work well closed up,—excavating to the
full depth as they go. Then, if they strike a stone too large to be taken
out within the terms of their contract, they can skip a sufficient
distance to pass it, and the digging of the omitted part may be done by a
faithful day workman. This will usually be cheaper and more satisfactory
than to pay the contractors for extra work.
[Illustration: Fig. 41 - FOOT PICK.]
Fig. 41 - FOOT PICK.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account