At that side of the swamp which lies nearest to the main depression of the
up-land, (See Fig. 21,) is the proper place at which to collect the water
from so much of the field as is now drained by the main brook, and at that
point it will be well to place a _silt basin_ or well, built up to the
surface, which may, at any time, be uncovered for an observation of the
working of the drains. The land between this point and the outlet is
absolutely level, requiring the necessary fall in the drain which connects
the two, to be gained by raising the upper end of it. As the distance is
nearly 200 feet, and as it is advisable to give a fall at least
five-tenths of a foot per hundred feet to so important an outlet as this,
the drain at the silt basin may be fixed at only 2-1/2 feet. The basin
being at the foot of a considerable rise in the ground, it will be easy,
within a short distance above, to carry the drains which come to it to a
depth of 4 feet,—were this not the case, the fall between the basin and
the outlet would have to be very much reduced.
*Main Drains.*—The valley through which the brook now runs is about 80
feet wide, with a decided rise in the land at each side. If one main drain
were laid in the center of it, all of the laterals coming to the main
would first run down a steep hillside, and then across a stretch of more
level land, requiring the grade of each lateral to be broken at the foot
of the hill, and provided with a silt basin to collect matters which might
be deposited when the fall becomes less rapid. Consequently, it is best to
provide two mains, or collecting drains, (_A_ and _C_,) one lying at the
foot of each hill, when they will receive the laterals at their greatest
fall; but, as these are too far apart to completely drain the valley
between them, and are located on land higher than the center of the
valley, a drain, (_B_,) should be run up, midway between them.
The collecting drain, _A_, will receive the laterals from the hill to the
west of it, as far up as the 10-foot contour line, and, above that
point,—running up a branch of the valley,—it will receive laterals from
both sides. The drain, _B_, may be continued above the dividing point of
the valley, and will act as one of the series of laterals. The drain, _C_,
will receive the laterals and sub-mains from the rising ground to the east
of it, and from both sides of the minor valley which extends in that
direction.
Most of the valley which runs up from the easterly side of the swamp must
be drained independently by the drain _E_, which might be carried to the
silt basin, did not its continuation directly to the outlet offer a
shorter course for the removal of its water. This drain will receive
laterals from the hill bordering the southeasterly side of the swamp, and,
higher up, from both sides of the valley in which it runs.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account