*Taking the Levels.*—For accurate work, it is necessary to ascertain the
comparative levels of the tops of all of the grade stakes; or the distance
of each one of them below an imaginary horizontal plane. This plane, (in
which we use only such lines as are directly above the drains,) may be
called the "Datum Line." Its elevation should be such that it will be
above the highest part of the land, and, for convenience, it is fixed at
the elevation of the levelling instrument when it is so placed as to look
over the highest part of the field.
_Levelling Instruments_ are of various kinds. The best for the work in
hand, is the common railroad level, which is shown in Fig. 6. This is
supported on three legs, which bring it to about the level of the eye. Its
essential parts are a telescope, which has two cross-hairs intersecting
each other in the line of sight, and which may be turned on its pivot
toward any point of the horizon; a bubble glass placed exactly parallel to
the line of sight, and firmly secured in its position so as to turn with
the telescope; and an apparatus for raising or depressing any side of the
instrument by means of set-screws. The instrument is firmly screwed to the
tripod, and placed at a point convenient for looking over a considerable
part of the highest land. By the use of the set-screws, the plane in which
the instrument revolves is brought to a level, so that in whatever
direction the instrument is pointed, the bubble will be in the center of
the glass. The line of sight, whichever way it is turned, is now in our
imaginary plane. A convenient position for the instrument in the field
under consideration, would be at the point, east of the center, marked
_K_, which is about 3 feet below the level of the highest part of the
ground. The telescope should stand about 5 feet above the surface of the
ground directly under it.
_The Levelling-Rod_, (See Fig. 7,) is usually 12 feet long, is divided
into feet and hundredths of a foot, and has a movable target which may be
placed at any part of its entire length. This is carried by an attendant,
who holds it perpendicularly on the top of the grade-stake, while the
operator, looking through the telescope, directs him to move the target up
and down until its center is exactly in the line of sight. The attendant
then reads the elevation, and the operator records it as the distance
below the _datum-line_ of the top of the grade-stake. For convenience, the
letterings of the stakes should be systematically entered in a small field
book, before the work commences, and this should be accompanied by such a
sketch of the plan as will serve as a guide to the location of the lines
on the ground.
The following is the form of the field book for the main drain _C_, with
the levels recorded:
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account