*The Depth and Grade of the Drains.*—Having now staked out the lines upon
the land, and ascertained and recorded the elevations at the different
stakes, it becomes necessary to determine at what depth the tile shall be
placed at each point, so as to give the proper fall to each line, and to
bring all of the lines of the system into accord. As the simplest means of
illustrating the principle on which this work should be done, it will be
convenient to go through with the process with reference to the main drain
_C_, of the plan under consideration. A profile of this line is shown in
Fig. 21, where the line is broken at stake No. 7, and continued in the
lower section of the diagram. The topmost line, from "Silt Basin" to "17,"
is the horizontal datum-line. The numbers above the vertical lines
indicate the stakes; the figures in brackets between these, the number of
feet between the stakes; and the heavy figures at the left of the vertical
lines, the recorded measurements of depth from the datum-line to the
surface of the ground, which is indicated by the irregular line next below
the datum-line. The vertical measurements are, of course, very much
exaggerated, to make the profile more marked, but they are in the proper
relation to each other.
The depth at the silt-basin is fixed at 2-1/2 feet (2.50.) The rise is
rapid to stake 3, very slight from there to stake 7, very rapid from there
to stake 10, a little less rapid from there to stake 11, and still less
rapid from there to stake 17.
To establish the grade by the profile alone, the proper course would be to
fix the depth at the stakes at which the inclination is to be changed, to
draw straight lines between the points thus found, and then to measure the
vertical distance from these lines to the line indicating the surface of
the ground at the different stakes; thus, fixing the depth at stake 3, at
4 feet and 13 hundredths,(15) the line drawn from that point to the depth
of 2.50, at the silt-basin, will be 3 feet and 62 hundredths (3.62) below
stake 1, and 3 feet and 92 hundredths (3.92) below stake 2. At stake 7 it
is necessary to go sufficiently deep to pass from 7 to 10, without coming
too near the surface at 9, which is at the foot of a steep ascent. A line
drawn straight from 4.59 feet below stake 10 to 4.17 feet at stake 17,
would be unnecessarily deep at 11, 12, 13, and 14; and, consequently it is
better to rise to 4.19 feet at 11. So far as this part of the drain is
concerned, it would be well to continue the same rise to 12, but, in doing
so, we would come too near the surface at 13, 14, and 15; or must
considerably depress the line at 16, which would either make a bad break
in the fall at that point, or carry the drain too deep at 17.
By the arrangement adopted, the grade is broken at 3, 7, 10, and 11.
Between these points, it is a straight line, with the rate of fall
indicated in the following table, which commences at the upper end of the
drain and proceeds toward its outlet:
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account