_Blasting combined with Dredging._--In some cases it has been found that
the bottom is too hard to be dredged until it has been to some extent
loosened and broken up. Thus at Newry, John Rennie, after blasting the
bottom in a depth of from 6 to 8 ft. at low water, removed the material
by dredging at an expense of from 4s. to 5s. per cub. yd. The same
process was adopted by Messrs Stevenson at the bar of the Erne at
Ballyshannon, where, in a situation exposed to a heavy sea, large
quantities of boulder stones were blasted, and afterwards raised by a
dredger worked by hand at a cost of 10s. 6d. per cub. yd. Sir William
Cubitt also largely employed blasting in connexion with dredging on the
Severn (see _Proc. Inst. C.E._ vol. iv. p. 362). The cost of blasting
and dredging the marl beds is given as being 4s. per cub. yd. A
combination of blasting and dredging was employed in 1875 by John Fowler
of Stockton at the river Tees. The chief novelty was in the barge upon
which the machinery was fixed. It was 58 ft. by 28 ft. by 4 ft., and had
eight legs which were let down when the barge was in position. The legs
were then fixed to the barge, so that on the tide falling it became a
fixed platform from which the drilling was done. Holes were bored and
charged, and when the tide rose the legs were heaved up and the barge
removed, after which the shots were discharged. There were 24 boring
tubes on the barge, and that was the limit which could at any time be
done in one tide. The area over which the blasting was done measured 500
yds. in length by 200 in breadth, a small part being uncovered at low
water. The depth obtained in mid-channel was 14 ft. at low water, the
average depth of rock blasted being about 4 ft. 6 in. The holes, which
were bored with the diamond drill, varied in depth from 7 to 9 ft., the
distance between them being 10 ft. Dynamite in tin canisters fired by
patent fuse was used as the explosive, the charges being 2 lb. and
under. The rock is oolite shale of variable hardness, and the average
time occupied in drilling holes 5 ft. deep was 12 minutes. The dredger
raised the blasted rock. The cost for blasting, lifting and discharging
at sea was about 4s. per cub. yd., including interest on dredging and
other plant employed. The dredger sometimes worked a face of blasted
material of from 7 to 8 ft. The quantity blasted was 110,000 cub. yds.,
and the contract for blasting so as to be lifted by the dredger was 3s.
1d. per cub. yd. A similar plan was adopted at Blyth Harbour (see _Proc.
Inst. C.E._ vol. 81, p. 302). The cost of the explosives per cub. yd.
was 1s. 4d., of boring 1s. 9d. per cub. yd., and of dredging 3s. per
cub. yd., including repairs, but nothing for the use of plant. The whole
cost worked out at 6s. 1d. per cub. yd. on the average.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account