buildings that were quite a distance apart and less liable to fire. I
told President Francis at this time that I was willing to submit a bid
for $76,600 on all the buildings shown in the specifications prepared by
Mr. Taylor. My first bid did not include all the buildings shown in the
specifications. I made this offer offhand. He asked me if I wanted to
figure on wrecking the buildings for the Exposition Company on a
percentage basis, they to own all the material and sell it and I to get
a per cent for doing the work. I told him I would take it by contract
for an agreed figure or would do the work for him on a percentage basis,
and that I would be glad to do anything for him I could. President
Francis said to me, "Mr. Krug, you put in your bid for $76,600 in
writing and have it in this office to-morrow morning." We were then
asked to wait out in the anteroom. We waited there until about 6
o'clock. At about 6 o'clock Mr. Taylor's secretary came in and announced
that the meeting had adjourned until the next day. We all left the room
then. At 10 o'clock the next morning, November 11, 1904, Mr. Schmitt and
myself went to Mr. Taylor's office, where I filed my bid in writing for
$76,600 to cover all the buildings shown in the specifications. We
waited there until about 4 o'clock, expecting some decision from the
salvage committee. About 4 o'clock Mr. Taylor's secretary came in and
announced that the meeting of the salvage committee had adjourned until
the following Monday.
The conditions embodied in the specifications as to the time allowed for
removal of the wreckage were so prohibitive as to render it almost
impossible to carry them out. The time limit--namely, three months--was
too short. It would entail an enormous expense and waste of material to
try to comply with the time conditions stated in the specifications.
The amount required by the specifications to be deposited in the form of
a certified check, payable to the Exposition Company, viz, 50 per cent
of the amount of bid, was very exorbitant. This check was to be
forfeited to the Exposition Company in the event the successful bidder
failed to enter into a contract with the salvage committee within five
days after they accepted the bid. I consider the amount demanded, 50 per
cent, very excessive, and it had the effect of frightening bidders away.
A 5 to 10 per cent deposit is usually the amount required by the
Government and the city.
The specifications also stipulated that the full amount of the contract,
less the amount of the certified check, held and to be appropriated by
the Exposition Company, must be paid to the Exposition Company at the
time the contract is signed. I consider this out of all reason, and in
itself would have a tendency to prohibit bidding.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account