It would be futile to profess, in the limits of a small work of this
kind, to instruct the beginner fully in the principles and practice of
mine surveying, especially as the most elaborate treatise can only be of
service when some actual practical experience and knowledge of
instruments have been obtained.
For an exhaustive and well-arranged work on the subject, Brough’s
“Treatise on Mine Surveying” can be strongly recommended, and should be
carefully studied by all wishing to learn the best methods of
accomplishing the accurate results that any mine-surveying worth the
name demands.
The following methods of connecting underground and surface work are
therefore addressed to such as are thoroughly acquainted with a dial and
the method of traversing.
1. =TO FIND WHERE A SHAFT SHOULD BE SUNK TO CONNECT WITH ANY PART OF THE
UNDERGROUND WORKINGS.=
Should the mine be one opened by an adit, there is no difficulty in
doing this, as the dial can be set up at the mouth and a sight taken to
a light; this can then, by means of the vertical arc, be prolonged up
the hill, and the remaining bearings and distances are then easily laid
down to the desired point. When a starting-point has been obtained, the
chief difficulty in these cases has been overcome. If a single shaft is
the only connection to the underground workings, the magnetic bearing of
the first line at bottom must first be carefully ascertained, and the
position of the first station brought to the surface by means of a
plumb-line, made of copper wire preferably, the plummet being put into a
dish of water to steady it. The dial is then set exactly over the end of
the line at the surface, and the first bearing and distance laid off.
Should it be impossible to set the instrument over the point at surface,
a spot must be found by trial outside the shaft which is in the correct
course. The dial is set up in the supposed direction of the line and
repeated sights taken to the first point till the instrument and it are
exactly in the required line, when the length of the first line can be
measured along it, and the new lines proceeded with.
As local attraction frequently affects the needle at the bottom of the
shaft, and so vitiates the surface survey that depends on its swinging
the same at both points, a method of dispensing with the needle must be
resorted to. This is the suspension of two plumb-lines from opposite
sides of the shaft, the plummets hanging exactly over as much of the
first underground line as the width of the shaft will allow.
The two plummet lines at surface then give the direction, and by trial
the dial must be put exactly in line with them in order to prolong it
correctly.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account