Building -- Estimates; Factories -- Design and construction; Hardware
Rubble masonry and stone backing are generally figured by the perch
or cubic yard. Dimension-stone footings are measured by the square
foot unless they are built of large, irregular stone, in which case
they are measured the same as rubble. Ashlar work is always figured by
the superficial foot; openings are usually deducted, and the jambs are
measured in with the face work. Flagging and slabs of all kinds, such
as hearths, treads for steps, etc., are measured by the square foot;
sills, lintels, molding, belt courses, and cornices, by the linear
foot; and irregular pieces, by the cubic foot. All carved work is done
at an agreed price by the piece.
DATA ON RUBBLE MASONRY
=24.= The following proportions and cost of materials and amount
of labor required to lay 1 perch of rubble masonry are reasonably
accurate, and will serve to give an idea of how to estimate such work.
A perch of rubble masonry requires, approximately, 2,500 pounds of
stone.
COST OF RUBBLE MASONRY
_Using 1-to-3 Lime Mortar_
1 perch of stone (25 cubic ft.) delivered at work $1.25
1 bushel of lime .25
⅙ cubic yard of sand, at $1.50 per cubic yard .25
½ day, mason’s labor, at $3.20 per day 1.60
¼ day, helper’s labor, at $2 per day .50
-----
Total $3.85
_Using 1-to-3 Portland-Cement Mortar_
1 perch of stone $1.25
¾ barrel of Portland cement, at $2 per barrel 1.50
¼ cubic yard of sand, at $1.50 per cubic yard .38
½ day, mason’s labor, at $3.20 per day 1.60
¼ day, helper’s labor, at $2 per day .50
-----
Total $5.23
To the preceding amounts should be added the cost of scaffolding and
the builder’s profit. If the walls are over two stories in height, 60
cents per perch extra for hoisting should be added.
DATA ON FLAGSTONES AND CURBING
=25. Flagstones= for sidewalks, ordinary stock, natural surface, 3
inches thick, with joints pitched to line, in lengths (along walk) from
3 to 5 feet, will cost, for a 3-foot walk, about 11 cents per square
foot (if 2 inches thick, 10½ cents); for a 4-foot walk, 12 cents; and
for a 5-foot walk, 16 cents. The cost of laying all sizes will average
about 3 cents per square foot. These figures do not include cost of
hauling.
Curbing, 4 in. × 24 in., granite, will cost from 40 to 50 cents per
linear foot at the quarry; digging and setting will cost from 10 to
12 cents additional; and the cost of freight and hauling must also be
added.
DATA ON ASHLAR AND CUT STONE
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account