Building -- Estimates; Factories -- Design and construction; Hardware
To the preceding prices of cut stone must be added the cost of setting,
which for water-tables, steps, etc. will be about 10 cents per linear
foot; and for window sills, etc., about 5 cents per linear foot. In
addition, about 10 cents per cubic foot for fitting, and about 5 cents
per cubic foot for trimming the joints after the pieces are set in
place, should be allowed.
=28.= In a day of 8 hours, a stone cutter can cut about 4 square
feet of granite, about 6 square feet of bluestone, or about 8 square
feet of Ohio sandstone or limestone. These figures are for 6-cut,
patent-hammered work. For rock-face ashlar (beds worked about 3 inches
from face, the rest pitched), a workman can dress from 15 to 25 square
feet of random ashlar per day; and from 18 to 20 square feet of coursed
ashlar. In dressing laminated stone, from two to three times more work
can be done in a day on the natural surface than on the edge of layers.
In figuring cut stone, ample allowance should be made for waste, which,
on an average, will be 15 per cent.
ADDITIONAL METHOD OF ESTIMATING ASHLAR
=29.= The following method of estimating the cost of cut stone is
employed by many practical stone men. It is based on the fact that
most ashlar walls have about the same number of sills, belt courses,
lintels, water-tables, etc. in proportion to their volume, and
therefore all the stonework, both the ashlar proper and the other
cut stone, may be lumped together at one price per cubic foot. For
estimating purposes, stone may be divided into two classes: _soft
stone_, such as the sandstones, and _hard stone_, such as the granites.
=30. Soft Stone.=—Indiana limestone may be taken as an example of soft
stone. In the Eastern Pennsylvania district, where the stone cutters’
wage rate is 50 cents per hour, the cost of this kind of stone is about
as follows:
Rough blocks, per cubic foot $ .75
Sawing, jointing, cutting, rubbing, waste in stock 1.50
-----
Total $2.25
If the work is tooled, which is preferable for this material, 20 cents
per cubic foot should be added. Thus the value in the yard, but ready
to set, for an ashlar front, including water-table, sills, lintels,
belt courses, all ordinary moldings, and plain cornices, is $2.45 per
cubic foot.
Consoles, dentils, panelings, and similar ornamental work, mantels,
and interior work have no fixed prices, but must be governed by the
estimator’s knowledge of time required to cut any particular kind,
sometimes reaching $5 per cubic foot. If moldings are deeply undercut,
an extra price will have to be charged.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account