Building -- Estimates; Factories -- Design and construction; Hardware
FILLING
CUBIC
_Quantities_ FEET
Around foundation walls, 181' 2" × 6" × 6' 6" 588.8
Around foundation of porches, etc., 142' 3" × 6" × 3' 213.4
-----
Total filling 802.2
_Cost_
The cost of excavation in sandy soil, taken from _Estimating and
Calculating Quantities_, Part 1, is 53 cents per cubic yard. The cost
of filling, including tamping, may be taken as about one-third that of
excavation, or, say, 18 cents per cubic yard.
_Summary_
Excavation, 14,296.2 cu. ft. = 529.5 cu. yd.,
at 53 cents per cubic yard $280.64
Filling, 802.2 cu. ft. = 29.7 cu. yd.,
at 18 cents per cubic yard 5.35
-------
Total cost of excavation and filling $285.99
STONEWORK
=3.= The foundation walls are built of rubble masonry to the sill at
the grade line, and from this sill to the water-table they are built
of ashlar with rubble backing, except those portions behind porches
and steps, which are wholly rubble. The estimate for stonework also
includes the concrete for footings and cellar floor; the number of
cubic feet of concrete required for the footings will be found by
referring to the item Excavation for Wall Footings.
RUBBLE MASONRY
CUBIC
_Quantities_[6] FEET
Cellar walls, 181' 2" × 1' 6" × 6' 6" 1,766.4
Add for extra thickness over 1' 6":
5" × 6' 3" × 6' 6" 16.9
1' 2" × 10' 8" × 6' 6" 80.9
----- 97.8
[7]Foundation walls for front porch:
74' 6" × 1' 8" × 1' 9" 217.3
74' 6" × 1' 2" × 9" 65.2
------ 282.5
Foundation for steps:
2 piers, 1' 6" × 1' 8" × 2' 6" 12.5
2 piers, 2' x 1' 6" × 2' 6" 15.0
----- 27.5
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account