One 4-inch lead bend 1.50
One 4-inch brass ferrule .35
10 ft. 2-inch lead waste pipe 2.50
14 ft. 1½-inch lead pipe 2.50
Twelve 2-inch brass ferrules 1.50
Two 2-inch lead traps 2.50
2 sq. ft. 6-pound sheet lead .90
Three 4-inch wire-basket strainers .40
20 lb. of wiping solder 5.00
-------
Total $185.15
LABOR
Labor, assumed to be one-fourth cost of all materials
= $584.15 × .25 = $146.04
_Summary_
Fixtures $315.00
Water-supply system 84.00
Drainage 185.15
Labor 146.04
-------
Total cost of plumbing $730.19
GAS-FITTING
=12.= Following is given the cost of buying and installing the
various gas fixtures and pipes that are used in the building under
consideration:
FIXTURES
_Quantities and Cost_
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account