=170. Grades of Putty.=—Putty is usually graded as follows:
_Commercial_, a very cheap grade; _pure_, a medium grade; and _strictly
pure_, the best grade, which is made of pure whiting ground in linseed
oil. The cheaper grades are made in the same manner, but with an amount
of adulteration, either in oils or whiting, commensurate with the cost.
Therefore, the cheaper the putty, the more it is adulterated, and none
but strictly pure should be used when good results are desired.
_White-lead putty_ is in a class by itself, and costs about twice as
much as strictly pure whiting putty; but where permanent glazing is
required, its use will show handsome returns on the investment.
ESTIMATING AND CALCULATING QUANTITIES
(PART 1)
INTRODUCTION
=1. Scope of Subject.=—The art of estimating is very important both to
the architect and to the builder; to the latter, in that he must employ
some systematic method of estimating in order to carry on his business
successfully, and to the former for the reason that he should at all
times be able to estimate the cost of the buildings that he designs.
The science—for such it is—of fixing prices on a piece of work in any
branch of the building trades must be based on an extended experience.
With a little practice, any one can learn to take off the quantities
of materials, but when it comes to determining the rates, only persons
having extensive and varied knowledge of building and costs of various
details can accurately estimate the time and labor required to
complete the work. In order, then, that the duties and requirements
of a practical estimator may be thoroughly understood, a number of
detailed estimates will be given in this Section as guides. It should
be remembered, however, that as the prices of materials and labor vary
from those assumed, so will the estimates vary. The information given
in detail should be considered only as a general guide in analyzing the
elements that enter into the constructive problems in each department
of the building trades. In this way it will be possible to determine
intelligently the various unit costs. The estimates given are, in
general, net figures, and do not include any contractor’s profit.
=2. Qualifications of the Estimator.=—In the United States, there are
no standard or definite rules on estimating that hold good in every
section. The builders of each locality have their own ideas and customs
regarding the subject. This fact, together with the difference in the
cost of labor in various parts of the country and the fluctuations
in the market price of materials, requires, as before remarked, that
a competent estimator be a man of long and varied experience in the
business. There are, however, certain practical rules and suggestions
that will materially assist in taking off the quantities and in valuing
the labor required for any building operation. These points will
therefore be taken up and considered in detail in this Section.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account