Building -- Estimates; Factories -- Design and construction; Hardware
=3. Important Factors.=—The prime considerations in making an estimate
are accuracy and time. To these ends the estimator must systematize
his efforts, and endeavor to do a maximum amount of work in a minimum
amount of time. This, however, should not be done at the expense of
accuracy, for accuracy is the most important factor and is only insured
when the figures are carefully checked. The estimator, therefore,
while avoiding too great refinements in calculation, should aim at
correctness rather than at speed in doing the work. Very frequently
do the effects of haste and inaccuracy in estimating the cost of a
structure become evident when it is too late to remedy the errors,
resulting sometimes in the financial ruin of the builder that trusts
too implicitly in the estimator’s figures.
A record should be kept of all estimates made, as this kind of
information is most valuable and establishes a precedent on which to
base subsequent estimates, as well as a check on the work at hand.
PRINCIPLES OF ESTIMATING
APPROXIMATE ESTIMATING
=4.= In order to make a preliminary estimate, before the plans of a
structure are drawn, but after the general dimensions of the proposed
building have been determined, architects and builders sometimes
employ a method of =approximate estimating=, by which the cost is
figured at so much per cubic foot of the building, the rate varying
according to its character and the finish required. The method is
also considerably used by insurance companies in fixing the amount to
be placed on a building. It should be borne in mind that this method
gives the approximate cost only, and should never be used in figuring
the contract price of a building. This estimate, however, may be used
to advantage in checking the accurate estimate, with which it will
frequently be found to agree remarkably well.
TABLE I
COST OF BUILDINGS PER CUBIC FOOT
==========================================+=============
| Cost
Class of Building | Cents per
| Cubic Foot
------------------------------------------+-------------
Small frame buildings, costing from $800 |
to $1,500 | 10 to 12
Frame houses, 8 to 12 rooms, costing from |
$1,500 to $10,000 | 12 to 15
Reinforced-concrete mill buildings | 10 to 14
Brick houses, 8 to 10 rooms | 15 to 18
Highly finished city dwellings, brick or |
stone | 20 to 25
Schoolhouses, brick | 12 to 20
Churches, stone | 20 to 40
Office buildings, well finished | 35 to 50
Hospitals, libraries, and hotels | 35 to 50
==========================================+=============
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account