Building -- Estimates; Factories -- Design and construction; Hardware
=Reinforced-concrete work= is also often measured by the cubic yard,
although sometimes it is contracted for as a finished building.
The steel reinforcement is sometimes included in the price. Often,
patented steel reinforcement is bought separately and delivered to the
contractor; at other times, the contractor buys the patented steel
or else makes it and pays a royalty to the holder of the patent.
Reinforced-concrete floors are sometimes measured by the cubic yard and
sometimes by the square yard, according to agreement. Pavements are
usually measured by the square foot or by the square yard.
In Table II are given the costs of stone concrete and gravel concrete.
These figures do not include builder’s profit, cost of superintendence,
or cost of forms. They are based on the following costs: Labor, 25
cents per hour; cement, $2 per barrel; sand, $1.50 per cubic yard;
crushed stone, $1.65 per cubic yard; gravel, $1 per cubic yard.
To the values given in the table, the price of the wooden forms,
both for material and erection, must be added. This of course varies
considerably, according to whether the work is straight or has a number
of corners and openings in it.
TABLE II
COST OF PLAIN STONE CONCRETE
===================+===================+===============================
Mixture | Quantity | Cost
------+-----+------+------+-----+------+------+-----+------+-----+-----
Cement|Sand |Broken|Cement|Sand |Broken|Cement|Sand |Broken|Labor|Total
Parts|Parts| Stone| Bar- |Cubic| Stone| | | Stone| |
| | Parts| rels |Yards| Cubic| | | | |
| | | | | Yards| | | | |
------+-----+------+------+-----+------+------+-----+------+-----+-----
1 | 2 | 4 | 1.5 | .45 | .90 |$3.00 |$.68 |$1.49 |$.75 |$5.92
1 | 3 | 5 | 1.1 | .50 | .85 | 2.20 | .75 | 1.40 | .75 | 5.10
1 | 3 | 6 | 1.0 | .45 | .90 | 2.00 | .68 | 1.49 | .75 | 4.92
------+-----+------+------+-----+------+------+-----+------+-----+-----
COST OF PLAIN GRAVEL CONCRETE
-------------------+-------------------+------------------------------
Mixture | Quantity | Cost
------+-----+------+------+-----+------+------+----+------+-----+-----
Cement|Sand |Gravel|Cement|Sand |Gravel|Cement|Sand|Gravel|Labor|Total
Parts|Parts|Parts | Bar- |Cubic|Cubic | | | | |
| | | rels |Yards|Yards | | | | |
------+-----+------+------+-----+------+------+----+------+-----+-----
1 | 2 | 4 | 1.3 | .4 | .80 |$2.60 |$.60|$ .80 |$.75 |$4.75
1 | 3 | 5 | 1.0 | .5 | .80 | 2.00 | .75| .80 | .75 | 4.30
1 | 3 | 6 | .9 | .4 | .85 | 1.80 | .60| .85 | .75 | 4.00
======+=====+======+======+=====+======+======+====+======+=====+=====
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account