These basic recommendations in further discussions evolved into an
integrated scheme of tremendous size and complexity, covering the entire
eastern half of the New Territories. It included a series of service
reservoirs and pumping stations along a main pipeline extending from
the Red China border to Kowloon. These would be linked to Plover Cove
and Hebe Haven by another system of tunnels. Virtually all the surface
rains in the eastern end of the New Territories would be fed through
catchwaters into the two main reservoirs. Since Hebe Haven might collect
more summer rain than it could hold, the excess water could be conveyed
by tunnel to Plover Cove, with its much larger capacity. Even the water
brought by pipeline from Red China would be fed into the integrated
system. Three balancing reservoirs, to maintain a controlled and even
flow of water, and two large new filtration plants, to purify the water
before it made the last stage of its journey to urban consumers, were to
become part of the system.
Many of the connecting pipelines were to be designed to convey water
in either direction, making the utmost use of storage capacity. By
these refinements of the original recommendations, the capacity of the
integrated scheme would be raised to 100 million gallons a day when it
came into full use.
The first stage of the gigantic new system had made remarkable progress
by the early part of 1962. The Lion Rock Tunnel had already been begun by
cutting through the side of a mountain to connect the filtration plant at
Sha Tin with a pair of service reservoirs in Kowloon. The tunnel, 32 feet
in diameter, will carry three pipelines, each four feet in diameter, and
a two-lane, 24-foot-wide auto road three-fourths of a mile through Lion
Rock Mountain. Excavation work on the Lion Rock Reservoirs, with a total
capacity of 41 million gallons, had almost been completed. At the other
end of the tunnel, at the Sha Tin filtration plant and pumping station,
a hillside site as extensive as four football fields had been excavated
and the spoil was being used to fill a shallow inlet. Construction of
ten miles of tunnels and the 10-foot-high Lower Shing Mun Dam were well
advanced.
Meanwhile, engineers were probing the soil structure at the entrance
of Plover Cove. Working from barges in 35 feet of water, they bored
down through 35 feet of soft clay, reaching to almost twice that depth
before they found impermeable clay and rock to form the foundation for
their earth-fill dam. When complete, the dam will extend 35 feet above
the water and 70 feet below it, with grouting to provide a watertight
foundation. The main section of the dam will cross the cove’s wide
entrance. Two shorter sections will close off side entrances to the cove.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account