7. =Serious Breaches.=--In case of serious breaches of main channels the
Subdivisional Officer to himself reach the spot as soon as possible.
8. =Breach Reports.=--See printed form M[62] attached. To be promptly
submitted for each breach to the Executive Engineer. The report contains
a column for cost of closure. This means the stoppage of the flow and
not the complete making up of the banks. The column for remarks of the
Executive Engineer should be filled in and the report promptly returned
to the Subdivisional Officer, who will, in the meantime, be making up
the banks and preparing a requisition or estimate.
[62] Not printed.
9. =Progress Report.=--With the Executive Engineer’s monthly progress
report a list of breaches will be submitted, canal by canal, with
columns showing date of occurrence and cost of closure. The return
should be on the attached form G.[63] The Subdivisional Officer should
also submit this form to the Executive Engineer.
[63] Not printed. The form differs slightly from a form prescribed by
the Chief Engineer for general use in the Province.
10. =Estimates.=--The cost of breaches is not to be charged to
maintenance estimates. At the close of each month the Executive Engineer
should submit or sanction an estimate, accompanied by the breach
reports, for closing any breaches which have occurred and making up the
banks.
11. =Breaches in the Flooded Area near Canal Heads.=--These may be of
special importance. It may be impossible to do any good and money may be
uselessly spent. In any such cases the Subdivisional Officer should at
once proceed to the spot and the case should be reported by wire to the
Executive Engineer and, if necessary, to the Superintending Engineer.
12. =Breaches in Flood Embankments.=--The Subdivisional Officer must at
once proceed to the spot and the case be reported by wire to the
Executive Engineer and Superintending Engineer. The Breach Report forms
can be submitted partially filled in at the earliest possible moment and
a complete form afterwards.
APPENDIX E.
SPECIFICATION FOR BUSHING.
(See page 139.)
1. The object of bushing is to form a silt berm and thus prevent or stop
the falling in of the banks.
2. The branches must be thickly packed in order that the water among
them may become still, and also in order that they may not be shifted by
the stream. If thickly packed, the pegs required will also be fewer.
Most of the branches should be leafy and freshly cut, but, mixed with
these, there may be a proportion of kikar or other leafless branches.
Frequently it is possible to utilise jungle trees of small value,
bushes, scrub jungle, or even long grass.
3. Except when the bushes are to be very small or the length to be
bushed very short, the proposed line for the edge of the berm should be
marked out by long stakes driven in the water at fairly close intervals.
Otherwise the work may be badly done and the berm formed imperfect and
out of line.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account