Much of the preliminary work necessary for the determination of
actual working plans was therefore completed in the summer and fall
of 1898, and when on December 12 a seemingly satisfactory contract
for the engines for the large aerodrome had been made it was thought
that rapid progress could be made on the constructional work after
January 1, 1899, when the allotment from the War Department would
become available.
[p133]
CHAPTER III
EXPERIMENTS WITH MODELS
Immediately after the contract for the engine had been placed and the
actual work had been begun, attention was given to the problem of
providing means for properly launching the aerodrome. On the theory
that the plan of launching the small aerodromes, which had finally
been adopted after many years of painstaking experiment, would be
the best to employ for the large aerodrome, Mr. Langley decided to
have constructed a large house-boat with the launching track arranged
on it in a way similar to that used for the small machines. While
the general plans for this boat had been under consideration for
some time, the actual working drawings were completed in January,
1899, and so great seemed the need for expediting its construction,
in order to have it ready at the time when the engine was expected,
that the contract which was made for its construction specifically
provided for its being completed promptly, there being a large
forfeit to cover any delay on the part of the contractor.
While the boat itself was being constructed, the working drawings
were completed for the house to be built on it, and a contract was
made for the construction of this house within a given period, there
being also a time forfeit in this contract.
When the end of February arrived, it was found that, although the
engine builder had succeeded in constructing an engine which weighed
one hundred pounds, and which theoretically should have given
something over twelve horse-power, yet he was unable to make it work
properly. And then began a protracted period of most exasperating
delays, the engine builder promising from week to week that certainly
within the succeeding ten days he would be able to make delivery of
the engine developing the full horse-power for which the contract
called. After this delay on the engine had continued for some
months—a delay which necessitated the cessation of the work on the
main steel frame of the aerodrome, as it was deemed best to make
certain tests of the engine running while supported by a portion of
the frame to determine whether or not it was strong enough before
completing the rest of it-—Mr. Langley decided to employ part of
the time in the construction of a model of one-eighth the linear
dimensions of the large aerodrome, which was to be used in testing
a model of the newly designed launching apparatus described later,
and which might also be flown as a kite in making check measurements
on the proper balancing which should be employed for the large
aerodrome. [p134]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account