_Excavation._—The cost of excavation depends on the character of the
material and on the amount of water present, the cost of pumping or
bailing the latter, if in large quantity, adding materially to the cost
of shovelling. The material through which the trenches are driven may
vary from a sand which can be shovelled without loosening, to solid rock
which must be blasted, an intermediate condition of soil being known as
hardpan and its excavation costing nearly as much time and effort as
rock itself. If the soil is sand, into which a shovel or spade can be
pushed without any picking of the material, the cost, as already stated,
will be about fifteen cents a cubic yard for shovelling, and if the
excavation is in trench and not more than six feet deep, the entire
trench can be excavated for seven and a half cents a lineal foot. It is
very unusual, however, to have conditions so favorable that such a low
price can be counted on. If the material requires picking, instead of
fifteen cents a cubic yard it will cost thirty cents a cubic yard, and a
trench two feet wide and six feet deep will cost fifteen cents a running
foot instead of seven and a half cents. If care is not taken at the
start to throw the dirt well back, it will be necessary to re-handle the
dirt from the bottom of the trench, throwing it back on the pile, and
this will add from five to ten cents a cubic yard, depending on what
proportion of the entire excavation has to be re-handled. In the
excavation for a tank, it is quite possible that the entire material may
have to be re-handled and the cost thus be increased by fifteen cents a
cubic yard. If the ground is very hard, as when boulders and clay are
intermixed, it may require twice as much time for loosening as for
shovelling, in which case the cost of digging the trench will be
forty-five cents a cubic yard, or twenty-two and a half cents per lineal
foot, with five or ten cents added if the material has to be re-handled.
If the material is a loose sand or gravel, the trench will probably
require sheeting, that is, boards or planks on each side of the open
trench with braces between, in order to prevent caving of the banks. If
new lumber has to be purchased for this purpose and its cost added to
the cost of excavation, an additional sum per cubic yard or per lineal
foot will be added, somewhat in proportion to the total amount of
excavation to be done. Finally, if the soil through which the trench is
being dug contains water, it may be necessary to have one or two men
continuously pumping during all the time that the excavation is going
on, and this also will add to the cost per cubic yard or per lineal foot
of the trench.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account