“That perseverance which has commanded success for England in so many
fields has achieved another triumph in New Zealand. For six years
has a quiet, but none the less remarkable, work been going on in the
range of hills that divides Christchurch from Lyttelton. Possessed of
a splendid harbour, the Province of Canterbury has had to suffer ever
since its foundation from the difficulty of communication between its
capital and port. At first sight the range of hills appear impassable,
and are sufficient to frighten new arrivals. For the first years of
the settlement’s existence there was nothing in the shape of a road
until the track over the hills was widened into a bridle path. All
goods destined for Christchurch had to be sent round in boats up the
river. Then came the cutting of a cart road winding round the hills,
and eventually reaching Heathcote (which may be properly called the
Christchurch side of the range). The latter road was opened in 1859,
and ever since the traffic on it has continued increasing. In 1856 an
attempt was made to introduce steam navigation on the river, for the
quicker and cheaper conveyance of goods, this unfortunately terminated
disastrously in the wreck of the steamship Alma. The course of the
river having been staked out in 1858, the Planet commenced running,
and from that time the number of coasting steamers has steadily
increased, while the sailing vessels from being confined to craft of
15 to 20 tons have risen to 100 tons. Still the great desideratum of
a _direct_ and _rapid_ communication remained, and various schemes
were propounded, but none carried into effect till May 1861, when
the Provincial Government accepted a tender from Messrs. Holmes &
Co., to complete a line of railway from Lyttelton to Christchurch (a
distance of six miles) in five years, for £240,500. In this contract
the tunnel, 2,838 yards long (the cost of which was estimated at
£195,000), was included. The first sod of the line was cut on the 17th
July, 1861, and for six long years, night and day, has the process of
boring through the mountain gone on. During that time the contractors
have met with all sorts of difficulties, not the least of which have
been the attractions offered to their men by the successive outbreaks
of the Otago and Canterbury diggings, but, lending their whole
energies to the task, the works have not been stopped for a single
day. The completion of this work must be productive of the highest
benefits to Canterbury.
It will thus be seen that this tunnel cost at the rate of £69 per
yard forward, and it required six years to complete it at a cost
both of money and time very onerous to a young settlement. With Mr.
Fell’s system the tunnel would have been altogether avoided, and it is
probable that the line would have been completed in about two years, at
a price not exceeding £60,000, instead of the £240,500 it has cost the
colony to construct it.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account