The rate of progress given in the foregoing Table is very different
from what was expected previous to the commencement of the works. It
was then anticipated that the tunnel would be excavated from end to end
before the close of 1864, but it was not until the 15th of October,
1866, or 9¼ years after operations had been begun, that exactly
one-half was perforated. On the 1st November, 1867, the half had been
exceeded by 1,958 metres, still leaving 4,152 metres to be excavated.
The amount of perforation accomplished on the two sides of the mountain
has always been unequal, for of the 4,152 metres yet to be excavated,
2,905, equal to about 1⅞ mile, have to be accomplished on the French
side, whilst on the Italian there are two-thirds of a mile. This will
be understood by an explanation of the strata through which the tunnel
is to be carried. Commencing at Modane, there are 2,140 metres of
schist, then 363 of quartz, followed by 2,706 of compact limestone, and
finally 901 of schist. This completes one half; the other, or Italian
half, is all schist. The only rock comparatively easy in working is the
schist, but from the commencement the schist on the French side was of
a more resisting character than that on the Italian. The miners came
upon the quartz exactly where they expected to find it, but instead of
its being a stratum 400 metres thick, as was anticipated, it turned out
to be only 363 metres; nevertheless, it required two years, less two
months, to bring it into subjection, that is, from the 15th of June,
1865, until the 20th of April, 1867,—the progress forward during all
that time, not much exceeding half a metre (about 20 inches) a-day. The
compact limestone nearest to the quartz having been partly decomposed
by the action of this latter, was very workable. Hence, during May and
part of June 1867, the advance was very considerable, but since June
the compact limestone has proved to be harder but not so difficult to
work upon as the quartz. For six weeks the engineers were hopeful that
they could go on at the rate of three metres a-day. If such progress
could have been unflinchingly maintained, the excavation on the French
side could have been accomplished by August 1870. With two metres a-day
it will require until March 1872; but if, the advance do not exceed a
metre and a-half a-day for two-thirds of the whole distance, the tunnel
cannot be perforated under six years, which brings the date to July,
1873.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account