3. =Reduction of Width.=--If a channel which is to be narrowed is
not a wide one, the reduction in width can be effected by any of the
processes described under bank protection (CHAP. VI.). But in a wide
channel, reduction of the width by any direct process is generally
impracticable. The expense would generally be prohibitive. Earth, if
filled in, is liable to be washed away unless protected all along.
Reduction in the width of a large channel is nearly always effected
either by groynes (fig. 26) or by training walls (fig. 27). Spurs or
short groynes for bank protection have been already described (CHAP.
VI., _Art. 2_). Groynes for narrowing streams are made in the same way
and of the same materials, but are longer. They are at right angles
to the stream or nearly so. Groynes in the river Sutlej have been
mentioned in CHAP. V., _Art. 5_, and are shown in fig. 6, p. 55.
Whether groynes or training walls are used, the object is to confine
the stream to a definite zone and to silt up the spaces at the sides.
These spaces when partly silted can be planted with osiers or with
anything which will grow when partly submerged, and this will assist in
completing the silting.
[Illustration: FIG. 26.]
[Illustration: FIG. 27.]
A training wall can be made of any of the materials used for groynes.
In order to silt up the spaces between each wall and the adjacent bank
of the stream, other walls are run at intervals across them. Usually
the training walls and cross walls are carried up only to ordinary
water-level, sometimes only to low-water level. Floods can thus spread
out and submerge the walls and deposit silt. If the walls are carried
up too high it may be necessary, in order to give room for floods,
to space them too far apart, and this, as will be seen below, is
objectionable.
The difference between training walls and groynes is one of degree
rather than one of kind. The material most commonly used is, in
either case, loose stone--with pitching, if desired, above low-water
level,--but it may be wattled stakes. If the water of the stream
contains silt at all stages of the supply, gaps can be left in training
walls so that silt deposit may occur at all times and not only in
floods. If the walls are of wattled stakes, water will pass through
them, and it may not be necessary to leave any gaps. Groynes are
frequently made with =T=-heads (fig. 26), and they are thus equivalent
to training walls with long gaps in them. The edge of the narrowed
channel usually forms somewhat as shown in the figure. If the groynes
are placed so near together as to give a regular channel, the cost is
not likely to be much less than that of training walls.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account