River and Canal Engineering, the characteristics of open flowing streams, and the principles and methods to be followed in dealing with them.Bellasis, E. S. (Edward Skelton)
Science
River and Canal Engineering, the characteristics of open flowing streams, and the principles and methods to be followed in dealing with them.
Bellasis, E. S. (Edward Skelton)
Canals; Hydraulic engineering; Rivers
While a dam is in course of construction arrangements must be made to
deal with flood water. Generally the construction of some part of the
dam has to be deferred to let the water pass. In the case of a masonry
dam it does not much matter what part is thus deferred provided the
usual procedure of stepping the work back is followed. In the case
of an earthen dam it is best to defer a portion, not in the lowest
ground where the dam is highest, but to one side of it, thus allowing
the highest part of the dam to be brought up continuously. Temporary
embankments and weirs can be constructed to cause the water to traverse
the desired route without doing damage. Stepping of the earthwork
should be avoided as far as possible. If it has to be adopted, the
steps should be small. Sometimes the flood water is conveyed away by
means of a “by-wash,” by an entirely different route.
[Illustration: FIG. 57.]
In Indian reservoirs the discharge over the waste weir may at times
be great. The waste weir is sometimes in the position shown in fig.
57, _a e_ being the weir. In such a case a special hydraulic problem
arises. In a case where a stream whose velocity is V issues from a
reservoir or takes off at right angles from a larger stream there is
(_Hydraulics_, CHAP. II., _Arts. 19_ and _20_) a fall in the water of
about V^2/2_g_. The same thing occurs downstream of a weir, at least
when there is a clear fall which is vertical or nearly so, so that the
water after falling has no horizontal velocity. The water has to be
started afresh on its course. In the case represented by the figure,
the width of the channel is often restricted because of high ground
beyond _f_, and the velocity in the channel may be very high. Suppose
the channel below _e f_ to be of brickwork with vertical sides, and
to have a 20-foot bed, a slope of 1 in 500, and a depth of water of
10 feet. The velocity may be 15 feet per second, and V^2/2_g_ is 3·49
feet. If the water has a clear fall over the weir at _e_, allowance
must be made for a depth of water of 13·49 feet, not 10 feet, in the
channel at _e_. Ordinarily the length _a e_ will be much greater,
relatively to _e f_, than shown in the figure. Suppose that _a e_ is
300 feet and that the slope of the floor of the channel is carried on
at 1 in 500 from _e f_ up to _a_, _b_, _c_, and _d_, following in each
case the lines marked on the figure which represent the directions of
flow. The length _f a_ will be about 310 feet, and the floor level
at _a_ will be about ·62 feet higher than at _e f_. The water-levels
below the weir will be in each case 13·49 feet above the floor. This
should be allowed for in the design. It is true that the stream on
first starting into horizontal motion below the weir moves more or
less at right angles to it, and has thus a large sectional area and a
low velocity; but it very soon has to turn parallel to the weir and
acquire the full velocity of 15 feet per second, and there must be the
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account