East end heading 126.00 feet
West shaft, east heading 33.00 "
" " west heading 5.00 "
West end 20.00 "
--------
Total for the month of November 184.00 "
Thirty feet of brick arch were completed during the month at the west
end, making a total of 516 feet of brick arch completed to date.
The progress for the last six months has been as follows:
East end 711.00 feet
West shaft, east heading 216.00 "
" " west " 288.00 "
West end 180.00 "
---------
Total, from June 1, to Dec. 2 1,395.00 "
" for the previous six months 632.00 "
---------
" " year ending Dec. 2, 1867 2,027.00 "
The new shaft has been sunk, and at its foot are the pumps which,
together with those at the west shaft, are now throwing out between 900
and 1,000 gallons of water per minute.
During the last month great quantities of water were struck at both
headings of the west shaft (70 gallons per minute at the east heading in
one day), and the work was stopped in consequence, which accounts for
the small progress at this point. A new pump of 1,000 gallons per minute
capacity will be at work, in addition to the above, in a few days, and
the work can then go forward with increased rapidity.
Well No. 4 is an artesian well, which is now being carried down as a
shaft to afford two more faces to work from. Its depth will be, when
finished, 215 feet, its dimensions 8 by 8 feet.
At the rate of progress for the past year it will require but eight
years and ten months to pierce through the mountain and at the rate for
the past six months it will require but six years and five months. But
when the central shaft and well No. 4 are sunk to grade the number of
faces to work from will be doubled, and the time of completion thereby
greatly diminished. At present drilling machines are employed only at
the east end, but in a few weeks they will be used at the west shaft,
and also at the central shaft as soon as the buildings and machinery are
again in place, and this again will hasten the completion of the work.
At the west shaft buildings are already erected for the manufacture of
nitro-glycerin, and the use of this powerful explosive will be adopted
during the present month. In fine, every means that will hasten the work
will be employed, and ere the present generation passes away, and
even within from four to seven years, trains loaded with freights and
passengers will pass and repass through the great heart of the Hoosac
Mountain as an hourly occurrence.
A. BEARDSLEY, C. E., Asst. Engineer.
North Adams, Mass.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account