=122. Unexpected Situations.=—When unexpected or uncertain conditions
are encountered in construction the engineer should visit the spot at
once and should advise or direct, according to the terms of the
contract, the procedure to be followed. Such conditions may be the
encountering of other pipes, quicksand, rock, etc. Each case is a
problem in itself. Water, gas, telephone and electric wire conduits can
be moved above or below the sewer being constructed with comparative
ease. Other sewers, if smaller, may be permitted to flow temporarily
across the line of the sewer under construction and finally discharge
into the completed sewer, or one sewer must be made to pass under the
other, either as an inverted siphon or by changing the grade of one of
the sewers. Rock, or other material for which a special rate of payment
is allowed, must be measured as soon as uncovered in order to avoid
delaying the work or losing the record of the amount removed. When
quicksand is met special precautions must be taken to safeguard the
sewer foundation and to insure that the sewer will remain in place until
after the backfilling is completed. These precautions are described in
Art. 135.
=123. Cost Data and Estimates.=—Cost account keeping and the making of
monthly or other estimates are closely connected. Cost accounts are of
value in estimating the amount of work done to date, and in making
preliminary estimates of the cost of similar work. Although the engineer
is not always required to keep such accounts, they are usually of
sufficient value to pay for the labor of keeping them. Under some
contracts the contractor’s accounts are open to examination by the
engineer. Usually, however, he must depend on reports from the
inspectors for information concerning the man-hours required on
different pieces of work, and on his own measurements of materials used
and his knowledge of their unit costs, in order to make up an estimate
of total cost.
The measurement of a completed structure and a summary of the materials
used in its construction may act as a check on the use of proper
materials as called for in the contract. For example, if it is known
that 2,000 bricks are required for the construction of a manhole and if
only 15,000 have been used in the construction of ten manholes, it is
probable that some or all of the manholes have been skimped. Similar
conditions may show in the proportions of concrete, backfilling in
tunnels, sheeting to be left in place, etc.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account