=124. Progress Reports.=[80]—These are kept by the engineer in order
that he may see that the work is progressing as called for in the
contract, and any portion which is lagging behind without reason may be
pushed. Such reports are most useful when the information is expressed
graphically, as the eye quickly catches points where the work is falling
behind schedule.
=125. Records.=—The contract drawings are supposed to show exactly where
and how construction is to be done. Due to unexpected contingencies
changes occur, of which a record should be made and preserved. These
records may be kept in a form similar to the contract drawings, or if
the changes are not extensive, they can be recorded on the original
contract drawings. The location of house and other connections should be
recorded in a separate note book available for immediate consultation.
The engineer should keep a diary of the work in which are recorded
events of ordinary routine as well as those of special interest and
importance. This diary should be illustrated by photographs showing the
condition of the streets before and after construction, methods of
construction, accidents, etc. Such accounts are of great value in
defending subsequent litigation and their existence sometimes prevents
litigation. A contractor may wait a year or so after the completion of a
piece of work until the engineer and other city officials have broken
their connection with the city. Suit is then brought against the city
and unless good records are available the administration may be forced
to buy the claimant off or may elect to enter court, only to be beaten.
[Illustration:
FIG. 88.—Samples of Cost Record Forms.
From Engineering and Contracting, 1909.
]
Excavation
=126. Specifications.=—The following abstracts have been taken from the
specifications on Excavation by the Baltimore Sewerage Commission as
illustrative of good practice. In conducting the work the contractor
shall:
... remove all paving, or grub and clear the surface over the
trench, whenever it may be necessary and shall remove all surface
materials of whatever nature or kind. He shall properly classify
the materials removed, separating them as required by the
Engineer; and shall properly store, guard, and preserve such as
may be required for future use in backfilling, surfacing, repaving
or otherwise. All macadam material removed shall be separated and
graded into such sizes as the Engineer may direct and materials of
different sizes shall be kept separate from each other and from
any and all other materials.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account