The opening of the trench may be facilitated by breaking ground with a
plow. In hard ground or on paved roads it may be necessary to cut
through the surface crust with a hammer and drill, although in some
cases a plow can be used successfully. Frozen ground can be thawed by
building fires along the line of the trench, or greater economy may be
achieved by placing steam pipes along the surface with perforations
about every 18 inches and either boxing them on the top and sides or
burying them in the frozen earth with a covering of sand. Another
arrangement is to blow steam into a line of bottomless boxes in which
each box is about 8 feet long. Holes are left in the top of the boxes
into which the pipe is shoved, and after its withdrawal the holes are
covered. Blasting of frozen earth is sometimes successful but cannot be
resorted to in built up districts where it is unsafe unless properly
controlled. Once the frost crust is broken through it can be attacked
from below and frequently broken down by undermining.
A laborer cannot dig and raise the earth much more than to the height of
his head, and preferably not quite so high, without tiring quickly.
After the trench has passed a depth of 4 feet he cannot throw the earth
clear of the trench. An additional laborer is needed then at the surface
to throw the earth back. He should shovel the earth from a board
platform placed at the edge of the trench as a protection to the bank.
When the trench passes the 6–foot depth a staging is put in about 4 feet
from the top on which the lowest laborer piles his materials. It is then
passed up to the surface by a second laborer on the staging, and a third
laborer on the surface throws the material back clear of the trench.
Stagings are put in about every 5 or 6 feet for the full depth of the
trench.
When the trench has come within half the diameter of the pipe of the
final grade, if the material is sufficiently firm, the remainder of the
trench should be cut to conform to the shape of the lower half of the
outside of the pipe, with proper enlargements for each bell.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account