The organization needed to operate these machines is: a lockman who
locks and unlocks the buckets on the cable, a dumper, as many shovelers
as there are buckets on the machine, and an engineman who is usually his
own fireman. From 50 to 400 cubic yards of material can be excavated in
a day with one of these machines, dependent on the character of the
material and the depth of the trench. H. P. Gillette in his Handbook of
Cost Data reports that about 190 cubic yards were excavated per day with
a Potter machine. The machine was 370 feet long. Six ¾-yard buckets were
used, 4 in the trench and 2 on the carrier. The trench was 10½ feet wide
and 18 feet deep in wet sand and soft blue clay. The organization
consisted of an engineman, a fireman, 2 dumpmen on the carrier, and from
17 to 21 excavating laborers depending on the kind and the amount of the
excavation. In general the capacity of such machines is limited by the
amount of material which can be shoveled into them by hand.
=132. Tower Cableways.=—These are essentially of the same class as the
trestle cableway machines. They differ in that the carriage supporting
the buckets travels on a cable suspended between 2 towers instead of on
a track supported on a trestle. As a rule only one bucket is handled in
the machine at a time. They are used in sewer work only in exceptional
cases as the towers must be taken down and re-erected each time that
there is an advance in the trench greater than the distance between the
towers.
=133. Steam Shovels.=—The use of steam shovels for the excavation of
sewer trenches is becoming more prevalent because of their growing
dependability and durability as compared with other machines, their
adaptability for small trenches, and the relatively large number of
widely different uses to which they can be put. In excavating a trench
the shovel straddles the trench and runs on tractors, wheels, or rollers
on either side of it. The shovel cuts the trench ahead of it. As a
result it is difficult to set sheeting and bracing close to the end of
the trench while the shovel is operating. Steam shovels are therefore
not suitable for excavation in unstable material, unless the sheeting is
driven ahead of the excavation. It is only in the softest ground that
ordinary wood sheeting can be driven ahead of the excavation. Steel
sheet piling is more suitable for such use. Fig. 93[84] shows a shovel
at work on a trench in Evanston, Illinois.
Shovels are equipped with extra long dipper handles to adapt them to
trench excavation. The dipper handle in the picture is longer than the
standard for this type of machine. The method of supporting the shovel
can be seen in the picture under the machine and the method of bracing
and of finishing the trench by hand work are also shown. The excavated
material is taken out in the shovel and dropped on the bank or into
wagons.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account