The method of placing poling boards is as follows: Excavate the trench
as far as the cohesion of the bank will permit. Poling boards, 1½ inch
to 2 inch planks, 6 inches or more in width, are then stood on end at
the desired intervals along each side of the trench for the length of
one ranger. The poling boards may be held in place by one or two
rangers. Two are safer than one but may not always be necessary. If one
ranger is to be used it is placed at the center of the poling board.
After the poling boards are in position the rangers are laid in the
trench and the cross braces are cut to fit. If wedges are to be used for
tightening the cross braces, the cross braces are cut about 2 inches
short. If jacks are to be used the braces are cut short enough to
accommodate the jacks when closed, or adjustable trench braces may be
used as shown in Fig. 106. The use of extension braces saves the labor
of fitting wooden braces. With everything in readiness in the trench,
the cross brace is pressed against the ranger which is thus held in
place. The wedge or jack is then tightened holding the poling boards and
cross brace in position.
[Illustration:
FIG. 106.—Box Sheeting.
Showing Different Types of Cross Bracing.
]
=153. Box Sheeting.=—Box sheeting is composed of horizontal planks held
in position against the sides of the trench by vertical pieces supported
by braces extending across the trench. The arrangement of planks and
braces for box sheeting is shown in Fig. 106. This type of sheeting is
used in material not sufficiently cohesive to permit the use of poling
boards, and under such conditions that it is inadvisable to use vertical
sheeting which protrudes above the sides of the trench while being
driven. This sheeting is put in position as the trench is excavated. No
more of the excavation than the width of three or four planks need be
unsupported at any one time. In placing the sheeting the trench is
excavated for a depth of 12 to 24 inches. Three or four planks are then
placed against the sides of the trench and are caught in position by a
vertical brace which is in turn supported by a horizontal cross brace.
[Illustration:
FIG. 107.—Vertical Sheeting.
]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account