=195. Reinforcement.=—It is essential that the reinforcement be held
firmly in place during the pouring of the concrete. A section of
reinforcement misplaced during construction may serve no useful purpose
and result in the collapse of the sewer. In sewer construction a few
longitudinal bars may be laid in order that the transverse bars may be
wired to them and held in position by notches in the centering and in
fastenings to bars protruding from the finished work. This construction
is shown in Fig. 1. The network of reinforcement is held up from the
bottom of the trench by notched boards which are removed as the concrete
reaches them, or better by stones or concrete blocks which are concreted
in. Sometimes the reinforcement is laid on top of the freshly poured
portion of the concrete the surface of which is at the proper distance
from the finished face of the work. This method has the advantage of not
requiring any special support for the reinforcement, but it is
undesirable because of the resulting irregularity in the reinforcement
spacing and position.
In the side walls the position of the reinforcement is fixed by wires or
metal strips which are fastened to the outside forms or to stakes driven
into the ground. Wires are then fastened to the reinforcement bars and
are drawn through holes in the forms and twisted tight. When the forms
are removed the wires or strips are cut leaving a short portion
protruding from the face of the wall. The reinforcing steel from the
invert should protrude into the arch or the side walls for a distance of
about 40 diameters in order to provide good bond between the sections.
The protruding ends are used as fastenings for the new reinforcement.
The arch steel may be supported above the forms by specially designed
metal supports, by small stones or concrete blocks which are concreted
into the finished work; or by notched strips of wood which are removed
as the concrete approaches them. Strips of wood are not satisfactory
because they are sometimes carelessly left in place in the concrete
resulting in a line of weakness in the structure. Metal chairs are the
most secure supports. They are fastened to the forms and the bars are
wired to the chairs. In some instances the entire reinforcement has been
formed of one or two bars which are fastened into position as a complete
ring. This results in a better bond in the reinforcement, requires less
fastening and trouble in handling, but is in the way during the pouring
of the concrete and interferes with the handling of the forms.
=196. Costs of Concrete Sewers.=—Under present day conditions a general
statement of the costs of an engineering structure can not be given with
accuracy. Only the items of labor, materials, and transportation that go
to make up the cost can be estimated quantitively, and the total cost
computed by multiplying the amount of each item by its proper unit cost
obtained from the market quotations.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account