=43. Layout of the Separate System.=—Upon completion of the preliminary
map a tentative plan of the system is laid out. The lines of the sewer
pipe are drawn in pencil, usually along the center line of the street or
alley in such a manner that a sewer will be provided within 50 feet or
less of every lot. The location of the sewers should be such as to give
the most desirable combination of low cost, short house connections,
proper depth for cellar drainage, and avoidance of paved streets. Some
dispute arises among engineers as to the advisability of placing pipes
in alleys, although there is less opposition to so placing sewers than
any other utility conduit. The principal advantage in placing sewers in
alleys is to avoid disturbing the pavement of the street, but if both
street and alley are paved it is usually more economical to place the
sewer in the street as the house connections will be shorter. On
boulevards and other wide streets such as Meridian Avenue in Fig. 24,
the sewers are placed in the parking on each side of the street, rather
than to disturb the pavement and lay long house connections to the
center of the street.
All pipes should be made to slope, where possible, in the direction of
the natural slope of the ground. The preliminary layout of the system is
shown in Fig. 24. The lowest point in the portion of the system shown is
in the alley between Alabama and Tennessee Streets. The flow in all
pipes is towards this point, and only one pipe drains away from any
junction, except that more than one pipe may drain from a terminal
manhole on a summit.
=44. Location and Numbering of Manholes.=—Manholes are next located on
the pipes of this tentative layout. Good practice calls for the location
of a manhole at every change in direction, grade, elevation, or size of
pipe, except in sewers 60 inches in diameter or larger. The manholes
should not be more than 300 to 500 feet apart, and preferably as close
as 200 to 300 feet. In sewers too small for a man to enter the distance
is fixed by the length of sewer rods which can be worked successfully.
In the larger sewers the distances are sometimes made greater but
inadvisedly so, since quick means of escape should be provided for
workmen from a sudden rise of water in the sewer, or the effect of an
asphyxiating gas. In the preliminary layout the manholes are located at
pipe intersections, changes in direction, and not over 300 to 500 feet
apart on long straight runs at convenient points such as opposite street
intersections where other sewers may enter.
No standard system of manhole numbering has been adopted. A system which
avoids confusion and is subject to unlimited extension is to number the
manholes consecutively upwards from the outlet, beginning a new series
of numbers prefixed by some index number or letter for each branch or
lateral. This system has been followed with the manholes on Fig. 24.
[Illustration:
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account