Sluices have their maximum discharge when set straight. Increased
grade may be given below any unavoidable curves with advantage, and
the outer side of the sluice must always be raised. Steps or "drops"
in the sluices help in the recovery of the gold. In general, a grade
of 6-6-1/2 inches to the 12-foot box is found best; this is equal to a
4-4-1/2 per cent. grade. Exceptional instances are on record, however,
where grades ran from 1-1/2 per cent. to 8 per cent. In a 4 to 7 per
cent. grade the water in the sluice should be 10 inches deep at least.
The following table gives useful details:
Sluice. Grade. Water.
6 ft. × 36 in. 4 to 5 p.c. 2,000 to 3,500 m. in.
4 ft. × 30 in. 4 p.c. 1,800 to 2,000 m. in.
3 ft. × 30 in. 1-1/2 p.c. 600 to 1,000 m. in.
"The longer the better," is the sluice-builder's motto. The best
"riffles" are made of blocks of pine 8 to 13 inches deep, wedged into
the bottom of the sluices. They are laid in rows separated by a space
of an inch or an inch and a half. Riffle strips keep them in position,
these latter being laid crosswise on the bottom. When worn down to
five inches, the blocks should be replaced. This amount of wear will
probably require six months. Stone and longitudinal riffles running
lengthwise of the box are often preferred.
An undercurrent is a broad sluice set at a heavy grade below the level
of the main sluice. The fine stuff drops through a grating, while the
coarse gravel continues on down the sluice.
Refuse material from quartz, hydraulic or other mines is known as
tailings. Tailings are deposited on a dump, which in the case of a
hydraulic claim must be sufficiently spacious to receive the thousands
of yards of debris deposited on it each day. When available a narrow,
deep canyon, or a tunnel, may take the places of dumps.
Quicksilver is used in the sluices, 14 to 18 flasks being used every
fortnight in a long sluice. It is not placed in the last 300 or 400
feet.
In working, keep the face of the bank "square." Washing should be
carried on continuously. Watches must be set over the sluices, or gold
is likely to be missed. As an extra precaution, the sluices should be
run full of gravel before shutting off the water. There is no fixed
custom regulating "clean ups." Some managers do so every 20 days,
others run two or three months, others again clean up but once in a
season. In large operations, the first 2,000 feet of sluice are
cleaned up every fortnight; the remaining boxes once a year.
Sluices are cleaned from the head downward, the blocks being taken up
for that purpose. The amalgam of gold and quicksilver is collected in
sheet iron buckets. The final step is reached when the amalgam is
retorted and melted in a graphite crucible.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account