manual labor in the same time. In the year 1862, however, in the three
hundred and twenty-five days of actual work, the advance made was
raised to three hundred and eighty metres (one thousand two hundred
and thirty-five feet), giving a mean advance of 1.17 metres, or about
three feet nine inches per day. In the year 1863, the length done
(always referring to the South or Bardonnêche side) was raised to
above four hundred metres; and no doubt this year a still greater
progress will have been made.
At the Fourneaux or Northern end of the tunnel--owing to increased
difficulties peculiar to the locality--the perforation of the gallery
was much delayed. A totally different system of mechanism for the
compression of air was necessitated; and it was not before the 25th of
January, 1863, that the boring-machine was in _successful_ operation on
this side, or two years later than at Bardonnêche. The experience,
however, gained at this latter place, and the transfer of a few
skilful workmen, soon raised the advance {65} made per day to an
amount equivalent to that effected at the Southern entrance. Thus, on
the South side (omitting the first year, 1861) since the beginning of
1862, and on the North side since the beginning of 1863, the new
system of mechanical tunnelling may be said to have been in regular
and _successful_ operation.
In the beginning of September of this year were completed in all three
thousand five hundred and seventy metres of gallery. From this we
deduct sixteen hundred metres done by manual labor, leaving, for the
work done by the machines, a length of nineteen hundred and seventy
metres. From this we can make a further deduction of the one hundred
and seventy metres executed in the first year of experiment and trial
at Bardonnêche, so that we have eighteen hundred metres in length
excavated by the machines in a time dating from the beginning of 1862
at the South end, and from the beginning of 1863 at the North end of
the tunnel. Thus, up to the month of September, 1864, we have in all
four years and six months; and eighteen hundred metres divided by 4.5
gives us four hundred metres as the rate of progress per year at each
side, or in total, eight hundred metres per year. Basing our
calculation, then, on this rate, we find that the eight thousand six
hundred and fifty metres yet to be excavated will require about ten
and a half more years; so that we may look forward to the opening of
the Mont Cenis tunnel at about the year 1875. The directing engineers,
who have given good proof of competency and skill, are, however, of
opinion that this period may be considerably reduced, unless some
totally unlooked-for obstacles are met with in the interior of the
mountain. As has been indicated above, sixteen hundred metres in
length of the tunnel was completed by manual labor before the
introduction of the mechanical boring-engines, in a period of five
years at the North and three years at the South side, equal to four
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account