When roughly prepared plans and elevations have been arranged on this
basis, the cubage can again be checked, and if it is over the allowed
amount, the size should be cut down; if under, increased. The cubical
contents of porches may be computed at one-quarter of the cubage of the
main portion of the house, but if enclosed with glass they should be
estimated at their full cubic contents.
Having thus roughly arrived at the plans and elevations of the house
which is within the allowed cubage, a rough outline specification
should be prepared in which the essential materials, workmanship, and
mechanical equipment are defined. Enough information will then be had
from which a rough estimate can be secured from a local contractor, or
even the architect may make an estimate, based upon previous examples
of other houses. If this rough estimate comes within the allowable
figure which is to be spent for construction, then the contract
drawings can be safely started, and a reasonable assurance can be had
that the cost of the house will not go beyond the amount of money
available. As most contractors will give an outside price on any
preliminary estimates of this kind, unless radical changes are made in
the plans, it can almost surely be the case that the final estimate on
the contract documents will be less. However, there are often times
when the final figures exceed these preliminary estimates, and one
should always be prepared to shrink parts of the building or withdraw
some of the finest requirements of the specifications.
But one of the prime essentials in financing any building operation
is to be sure that the contract drawings contain everything which is
desired in the finished building, and that none or very few changes
are made in the building after the contract is let and the building
is in process of construction. Alterations from the original plans,
after construction work has begun, come under the bugbear title for
all architects, “Extras.” They always mean waste of money. Likewise,
things which were omitted from the plans and specifications, which
are later found to be necessary, run up extraordinary bills, and the
general impression which most people have that a building operation
always costs more in the end than was originally counted upon is due
largely to the neglect of these factors. Competent architects make such
complete plans and specifications that extras of the “omission type”
are avoided, but most small houses are built from plans that are not
complete, or prepared by architects who sell their services at such low
rates that they cannot afford to take the time to check up the plans
carefully. It is right here that the architect has a real business
point to give the client, namely, that if he does not pay for carefully
prepared plans and specifications in the beginning, he will pay out
much more in the end for extras.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account