When the contract is finally let, there are a number of things which it
should cover that are intended to protect the finances of the owner.
For instance, the contractor should be required to maintain insurance
that will protect him from the claims under workmen’s compensation
acts, and from any other claims for damages for personal injury,
including death, which might arise from the operations of building. The
owner should also maintain a similar liability insurance to protect
himself.
The owner should carry a fire insurance on the entire building and
materials to at least 80 per cent of the total value.
When there is doubt as to the financial strength of a contractor, he
should be required to furnish a bond covering the faithful performance
of the contract and the payment of all obligations.
Then, too, it is customary to set forth cash allowances in the
specifications to cover certain items, like plumbing fixtures,
hardware, and electric light fixtures. The contractor should be made to
declare that the contract sum includes these cash allowances.
Careful understanding with the contractor should be arranged as to the
method by which he will be paid. Generally, as was previously stated,
the financing institution has control over the schedule of payments,
and, once this is agreeable to the contractor, he should be required to
submit to the architect an application for each payment, with receipts
and other vouchers, showing his payments for materials and labor,
including payments to subcontractors, at least ten days before each
payment falls due. It is the duty of the architect to determine the
accuracy of each one of these applications for payment before he issues
the certificate of payment for such amount as he decides is properly
due. There are some architects who make it a practice to hold back a
certain percentage of the first payment, and continue this with every
later payment, until the last, in order to have a club over the head
of the contractor and also a factor of safety, lest the builder has
rendered an application for payment in excess of the amount of labor
and material delivered. This, of course, will cause hard feelings
sometimes, and create friction between architect and contractor, a
thing studiously to be avoided, and for this cause such procedure
should be dropped when the architect knows the character of the
contractor.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account