that Sir Charles took advantage of that increase of taste for
artistic beauty and magnificence, which had grown up since his
designs were originally formed. In any case the expenditure on this
head must fairly be regarded, as in very great degree unconnected
with the first estimate, and deserving to be judged on its own
merits.
(_b._) It should next be noted that nearly 208,000_l._ was taken up
by the arrangements for warming and ventilation, and for the extra
work in fire-proofing which they rendered necessary.
The largeness of this amount will surprise no one who remembers
that for these arrangements one-third of the cubical contents of
the building was demanded; that the Central Tower itself belongs to
these extra works; that large portions of the building were carried
up for the purpose of providing continuous air and smoke flues, in
the cross roofs connecting those in the main building; and that
great changes of material were introduced, such as the substitution
of iron for slated roofs, and of iron girders and brick arches for
ordinary floors.
(_c._) Besides these two chief causes of increased expenditure, it
must be added, that the purchase of extra site and the cost of
works (such as the river wall) expressly excepted from the
estimate, absorbed nearly 170,000_l._, and that a sum of 97,000_l._
was devoted to purposes connected with the building, but not
properly forming part of the works.
These sums amount in all to 970,000_l._ The rest of the excess is
really and properly connected with the works, on which the
estimate was made. On this it is right to observe--
(_a._) That the treacherous nature of the soil, discovered after
the estimate was made, necessitated a large increase of expense on
the foundations (nearly 50,000_l._).
(_b._) That the failure of the Bolsover stone, and the employment
of the harder Anston stone, involved a great increase of labour
upon it, and therefore of expense.
(_c._) That the very fact, already noticed, of the piecemeal
occupation of the building, necessitating all kinds of temporary
arrangements, obstructing progress, and often preventing work from,
being done in the easiest and simplest manner, also tended in the
same direction.
(_d._) That large additional requirements were made for the public
service in the course of the erection of the building, including
the restoration of St. Stephen’s Crypt, the provision of residences
for the Clerk of the House of Commons, the Clerk of the Crown, the
gentlemen in charge of the ventilation of the building, &c.
(_e._) That the upward tendency of prices of labour and material,
within the time occupied by the erection of the building, naturally
told against the public, and very greatly increased the needful
expenditure.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account