The 5th and last ground alleged by the Commissioners of Woods in support
of the Government proposition is, “The period within which it was
proposed that the contemplated expenditure should be incurred.” This
ground was assigned upon the assumption that the entire edifice might be
completed within six years; but, owing to the limited portions of the
site that could from time to time be cleared, in consequence of the
necessity which has constantly existed of providing accommodation for
the business of Parliament upon a part of that site, it was found to be
impossible, particularly in the early stages of the work, to employ an
unlimited number of men, or to expend more upon an average than between
80,000_l._ and 90,000_l._ per annum. On this account, and also in
consequence of the delays and difficulties occasioned by the
extraordinary nature and extent of the warming and ventilating
arrangements, and the difficulty of complying with Dr. Reid’s
requirements in respect of them, the peculiar nature of the site, the
difficulty of obtaining accurate information as to the ever-varying
accommodation required, the delay in official communications and in
obtaining authorities, and the limitation of the supplies of late years,
the time occupied upon the works has already amounted to nearly twice
the period originally assumed for their completion; and it is obviously
impossible, while such contingencies are likely to impede their
progress, to say how much longer it will be before the entire work will
be completed.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account