The tube is made oval in section with the greater diameter horizontal,
in order that it may have stiffness sideways under the compressive
strain, and that the main chains may hang vertically at such a distance
as to leave room for the roadway between them. The tube is 16 feet 9
inches broad and 12 feet 3 inches in height. Each chain consists of two
tiers of links, each tier formed of 14 and 15 links alternately. These
are 7 inches deep and about 1 inch thick. The arrangements of the
ironwork of the tube and its connections with the main chains are
generally similar to those at Chepstow.
The truss may be described as a combination of an arch and a suspension
bridge, half the weight being placed on the one and half on the other,
the outward thrust of the arch on the abutments being counterbalanced by
the inward drag of the chains.
The mechanical arrangement of the Saltash truss is similar to that of
the one at Chepstow.[110] The tube, resting on standards, the railway
passing beneath, the suspension chains hung from either side of the
tube, the upright standards, and the diagonal bracing are common to the
two structures.
The difference in the form of the two trusses is principally the result
of the difference in the circumstances attending the construction of the
bridges at Chepstow and Saltash. The design of the Chepstow truss was
chiefly determined by the necessity of lifting up the separate parts of
it under conditions of peculiar difficulty; while at Saltash the mode of
floating and lifting the superstructure had great influence in the
preparation of the design.
On Plate V. (p. 218) is given an elevation of one span of the Saltash
bridge, and a general elevation on a smaller scale of the whole bridge.
The total weight of wrought ironwork in the superstructure of each span
is 1,060 tons.[111]
The trusses at Saltash were not lifted in parts, as at Chepstow; for,
as the river was divided by the centre pier into two openings, one of
them could be left clear for the navigation, and each truss, with its
roadway girders attached, could be raised to its position slowly and in
one piece. The trusses were constructed parallel to the river on the
Devonshire side, close to the site of the bridge. When the truss for the
Cornwall or western span was completed, temporary piers were erected to
support the ends, and the scaffolding having been removed, the roadway
was loaded with 1,190 tons, uniformly distributed.[112]
This test having proved satisfactory, preparations were made for
floating the truss. Docks were made underneath it near the two ends, and
in each of these docks two iron pontoons were placed. Valves were then
opened to admit water, and the pontoons were allowed to sink on timbers
prepared to receive them.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account