He also devised means, by levers and hydraulic presses, for relieving
the rollers and roller beds from pressure, in the event of their
requiring renewal.
Mr. Brunel ultimately determined to adopt the Egyptian style of
architecture. His brother-in-law, Mr. John Callcott Horsley, R.A., gives
the following account of the proposed designs for the towers:--
‘His conception of the towers or gateways at either end of the bridge
was peculiarly grand and effective, as may be seen from his sketches
still existing. They were to be purely Egyptian; and, in his design, he
had caught the true spirit of the great remains at Philæ and Thebes. He
intended to case the towers with cast iron, and, as in perfect
accordance with the Egyptian character of his design, to decorate them
with a series of figure subjects, illustrating the whole work of
constructing the bridge, with the manufacture of the
materials--beginning with quarrying the iron ore, and making the iron,
and ending with a design representing the last piece of construction
necessary for the bridge itself. The subjects would have been arranged
in tiers (divided by simple lines) from top to bottom of the towers, and
in the exact proportion of those found upon Egyptian buildings. He made
very clever sketches for some of these proposed figure subjects, just to
show what he intended by them. I remember a group of men carrying one of
the links of the chainwork, which was excellent in character. He
proposed that I should design the figure subjects, and he asked me to go
down with him to Merthyr Tydvil, and make sketches of the iron
processes. We accomplished our journey, and all the requisite drawings
for the intended designs were made.’
The works were commenced with the Leigh abutment, which was completed in
1840, great delay having been caused by the failure of the contractors.
This misfortune led to a large excess of expenditure over the original
estimates. In 1843 the whole of the funds raised (amounting to
45,000_l._) were exhausted, and there still remained to be executed the
ornamental additions to the piers (the cost of which was estimated at
about 4,000_l._), half of the iron work, the suspension of the chains
and rods, the construction of the flooring, and the completion of the
approaches, &c., the estimate for the execution of which was 30,000_l._
Unfortunately, all efforts to raise further subscriptions were
unsuccessful; and in July 1853, when the time limited for the completion
of the bridge had expired, the works were closed in, and the undertaking
abandoned.[35]
Several proposals for completing the bridge were made in Mr. Brunel’s
lifetime, and he took every opportunity of furthering this object, which
he had very much at heart. It was not, however, till about a year after
his death that the superstructure of the bridge was actually commenced.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account