A careful specification of the masonry work was drawn up, and the
contract was let to Messrs. Stapleton and Hall; but as they did not
proceed satisfactorily, and desired to be released from the contract,
it was relet on the same terms to Mr. John Wilson, one of Mr. Telford's
principal contractors for mason work on the Caledonian Canal.
The building operations were begun with great vigour early in 1820.
The three arches on the Caernarvonshire side and the four on the
Anglesea side were first proceeded with. They are of immense
magnitude, and occupied four years in construction, having been
finished late in the autumn of 1824. These piers are 65 feet in
height from high-water line to the springing of the arches, the
span of each being 52 feet 6 inches. The work of the main piers
also made satisfactory progress, and the masonry proceeded so
rapidly that stones could scarcely be got from the quarries in
sufficient quantity to keep the builders at work. By the end of
June about three hundred men were employed.
The two principal piers, each 153 feet in height, upon which the
main chains of the bridge were to be suspended, were built with
great care and under rigorous inspection. In these, as indeed in
most of the masonry of the bridge, Mr. Telford adopted the same
practice which he had employed in his previous bridge structures,
that of leaving large void spaces, commencing above high water mark
and continuing them up perpendicularly nearly to the level of the
roadway. "I have elsewhere expressed my conviction," he says, when
referring to the mode of constructing these piers, "that one of the
most important improvements which I have been able to introduce
into masonry consists in the preference of cross-walls to rubble,
in the structure of a pier, or any other edifice requiring strength.
Every stone and joint in such walls is open to inspection in the
progress of the work, and even afterwards, if necessary; but a
solid filling of rubble conceals itself, and may be little better
than a heap of rubbish confined by side walls." The walls of these
main piers were built from within as well as from without all the
way up, and the inside was as carefully and closely cemented with
mortar as the external face. Thus the whole pier was bound firmly
together, and the utmost strength given, while the weight of the
superstructure upon the lower parts of the work was reduced to its
minimum.
[Image] Section of Main Pier
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account