A similar method of anchoring the main chains was adopted on the
Caernarvonshire side. A thick bank of earth had there to be cut
through, and a solid mass of masonry built in its place, the rock
being situated at a greater distance from the main pier; involving
a greater length of suspending chain, and a disproportion in the
catenary or chord line on that side of the bridge. The excavation
and masonry thereby rendered necessary proved a work of vast
labour, and its execution occupied a considerable time; but by the
beginning of the year 1825 the suspension pyramids, the land piers
and arches, and the rock tunnels, had all been completed, and the
main chains were firmly secured in them; the work being
sufficiently advanced to enable the suspending of the chains to be
proceeded with. This was by far the most difficult and anxious part
of the undertaking.
With the same careful forethought and provision for every
contingency which had distinguished the engineer's procedure in the
course of the work, he had made frequent experiments to ascertain
the actual power which would be required to raise the main chains
to their proper curvature. A valley lay convenient for the purpose,
a little to the west of the bridge on the Anglesea side.
Fifty-seven of the intended vertical suspending rods, each nearly
ten feet long and an inch square, having been fastened together, a
piece of chain was attached to one end to make the chord line 570
feet in length; and experiments having been made and comparisons
drawn, Mr. Telford ascertained that the absolute weight of one of
the main chains of the bridge between the points of suspension was
23 1/2 tons, requiring a strain of 39 1/2 tons to raise it to its
proper curvature. On this calculation the necessary apparatus
required for the hoisting was prepared. The mode of action finally
determined on for lifting the main chains, and fixing them into
their places, was to build the central portion of each upon a raft
450 feet long and 6 feet wide, then to float it to the site of the
bridge, and lift it into its place by capstans and proper tackle.
At length all was ready for hoisting the first great chain, and
about the middle of April, 1825, Mr. Telford left London for Bangor
to superintend the operations. An immense assemblage collected to
witness the sight; greater in number than any that had been
collected in the same place since the men of Anglesea, in their
war-paint, rushing down to the beach, had shrieked defiance across
the Straits at their Roman invaders on the Caernarvon shore.
Numerous boats arrayed in gay colours glided along the waters; the
day--the 26th of April--being bright, calm, and in every way
propitious.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account