In order to assist town surveyors who may be required to act under this
clause, I now give a verbatim copy of a “plan” or specification under
which I compelled a gas company to work after they had given me the
usual statutory notice of their intention to break up certain
macadamised streets for the purpose of removing some disused mains.
_Plan of the manner in which the Gas Light and Coke
Company shall take up and remove the old mains in street,
commencing at or near street._
A trench to be excavated of not greater width than inches and of no
greater length than feet at a time.
Great care must be taken to keep the top facing metal separate from the
lower formation of the roadway, so that they may not become mixed
together; no metal is on any account to be removed from the street.
The mains must be taken up with all possible speed and instantly
conveyed away, without being allowed to remain at the sides of the
streets.[129]
The trench to be then at once filled in, care being taken to replace all
the materials of which the roadway is formed in their proper positions.
All extra filling in that may be required owing to the removal of the
mains shall be done on the surface with the best stone, broken
so as to pass all ways through a ring of 2¹⁄₂ inches internal diameter,
the top of the trench being always kept flush with the surface contour
of the roadway. No earth, rubbish, or other material shall be allowed to
be brought on to the ground by the gas company for the purpose of
filling in, nor shall any material of any kind be allowed to be brought
from any other excavations that may be being made by the gas company in
other parts of the town for the purpose of laying or removing mains.
The filling in to be done in the proportion of one man filling to two
men ramming with punners of not less weight than lbs. each. During
dry weather a plentiful supply of water must be allowed to run into the
trench whilst the filling in is in progress, for the purpose of
consolidating the ground.
The traffic must not in any case be impeded, and planks must be placed
across the excavations, where necessary, for the convenience of foot
passengers.
The work shall if necessary be suspended on market days, or any other
days that the surveyor may deem proper for the convenience of the
public.
* * * * *
The next clause of the Act deals with the manner in which the companies
shall reinstate and make good the road or pavement, and is as follows:
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account